Providing and fixing insulating board ceiling of approved quality with necessary nails etc. complete (frame work to be paid separately) : Natural colour insulating board

12 mm thick
Item number
12.24.1.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹924.35/ SQM
D-01/RATE ANALYSISITEM 12.24.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.24.1.1 (Providing and fixing insulating board ceiling of approved quality with necessary nails etc. complete (frame work to be paid separately) : Natural colour insulating board 12 mm thick) is derived from 7 priced inputs for 10 sqm and works out to ₹924.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including 10% wastage = 11.00 sqm
ANALYSIS OF RATES · ITEM 12.24.1.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0332MATNatural colour insulating board:12 mm thickNatural colour insulating board: 12 mm thicksqm11231.002,541.00
9977MATCarriage of materialL.S.17.552.2739.84
9999MATNailsL.S.26.912.2761.09
0111LABCarpenter 1st classday2.5897.002,242.50
0114LABBeldarday2736.001,472.00
9999MATScaffoldingL.S.31.072.2770.53
9999MATSundriesL.S.31.072.2770.53
BUILD-UP TO RATE
TOTAL
6,497.49
Add 1 % Water charges on “W”
+64.97
TOTAL
6,562.46
Add GST on “X” (multiplying factor 0.2127)
+1,395.84
TOTAL
7,958.30
Add 15% CPOH on “Y”
+1,193.75
TOTAL
9,152.05
Add Cess @ 1% on “Z”
+91.52
Cost of 10.00 sqm.
9,243.57
Cost of 1.00 sqm.
924.36
SAY
₹924.35
D-02/SOURCEPRINTED PAGE 881
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
881

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 881. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.