R/DAR 2023

Providing sand stone slab for roofing and laying them in cement mortar 1 : 4 (1 cement : 4 coarse sand) over wooden karries or R.C.C. battens or structural steel sections (Karries or battens or structural steel sections to be paid separately), including pointing the ceiling joints with cement mortar 1:3 (1 cement : 3 fine sand ) complete : White sand stone slab

40 to 50 mm thick
Item number
12.23.2.1
Analysis basis
100 sqm
Priced inputs
8
Derived rate
₹1,106.90/ SQM
D-01/RATE ANALYSISITEM 12.23.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.23.2.1 (Providing sand stone slab for roofing and laying them in cement mortar 1 : 4 (1 cement : 4 coarse sand) over wooden karries or R.C.C. battens or structural steel sections (Karries or battens or structural steel sections to be paid separately), including pointing the ceiling joints with cement mortar 1:3 (1 cement : 3 fine sand ) complete : White sand stone slab 40 to 50 mm thick) is derived from 8 priced inputs for 100 sqm and works out to ₹1,106.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • including wastage @ 10% = 110 sqm
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Cement mortar for grouting 1:3 (1 cement :
  • 3 fine sand)
ANALYSIS OF RATES · ITEM 12.23.2.1DETAILS OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1175MATWhite sand stone slab 45 mm and 50 mm thick (un-dressed)White sand stone slab 45 mm to 50 mm thick (un-dressed)sqm110320.0035,200.00
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.0954,211.70400.11
0155LABMason (average)day15.2857.0013,026.40
0100LABBandhaniday18.2816.0014,851.20
0115LABCoolieday15.2736.0011,187.20
0101LABBhistiday3816.002,448.00
9999MATSundriesL.S.161.22.27365.92
SUBRate as per Item Number 3.3 of SH: MortarsRate as per item 3.3cum0.0754,379.05328.43
BUILD-UP TO RATE
TOTAL
77,807.26
Add 1 % Water charges on “W”
+778.07
TOTAL
78,585.33
Add GST on “X” (multiplying factor 0.2127)
+16,715.10
TOTAL
95,300.43
Add 15% CPOH on “Y”
+14,295.06
TOTAL
1,09,595.49
Add Cess @ 1% on “Z”
+1,095.95
Cost of 100 sqm.
1,10,691.44
Cost of 1 Sqm.
1,106.91
SAY
₹1,106.90
D-02/SOURCEPRINTED PAGE 880
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
880

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 880. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.