Skip to main content

CPWD Analysis of Rates · Roofing

Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (up to any pitch in horizontal/ vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required

0.80 mm thick with zinc coating not less than 275 gm/m²

Item number
12.1.2
Analysis basis
Details of cost for a roof with each sloping
Priced inputs
21
Derived rate
1,257.55 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.1.2 Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (up to any pitch in horizontal/ vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required 0.80 mm thick with zinc coating not less than 275 gm/m² — is derived from 21 priced inputs for a roof and works out to ₹1,257.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • side 18.09x5.10m and slop being flatter than
  • 1 vertical to 2.5 horizontal
  • Area of roof = 2x18.09x5.1 = 184.518 sqm.
  • Details of length and breadth.
  • Length 26(laps)x0.135(each lap)=3.51
  • Width of Corrugator sheet with 10
  • corrugation measured end to end = 0.8 metres 27 (nos. of sheets)x0.80 (width of sheet)
  • = 21.60 length
  • Length = 18.09
  • Breadth on one sideC.G.S. Sheet 1 No. of = 2.5 metres length+
  • C.G.S. Sheet 1 No. of = 2.8 metres length
  • Total = 5.3 metres
  • breadth = 5.1m
  • C.G.S. Sheets 0.8mm thick
  • 2x27=54nos. @15.82Kg.each
  • Total = 854.38Kg(X)
  • 2.5mx0.9m is the size of plain G.I.sheet
  • which on being corrugated will become
  • 2.5mx0.8m (The size of plain sheet is taken
  • because the weight is available only of plain
  • sheets) (Refer I.S. Code 277-1962)
  • 2x27=54nos. of size.
  • 2.8x0.9@17.72Kg each = 956.8Kg (Y)
  • Total of (X)+(Y) = 1811.16Kg.
  • Total = 1901.72Kg = 19.02q
  • G.I.Seam bolts and nuts 60cm
  • centre to centre zig-zag i.e. 30cm
  • centre to centre straight
  • Breadth is 5.1metre
  • No. of bolts in one lap 5.1/0.3 =17 nos.
  • 2x26(laps)x17 nos. = 884 nos.
  • (No. of purlins to be used 5 on either
  • side)2x5x27 (No. of sheets)x23 Nos. of bolts
  • in each sheet = 810 Nos
  • (total of seam and J bolts)
  • 884+810=1694
  • Less laps = 3.51
  • Deduct end lap of 20cm (-)0.2 metres
  • Add wastage @5% = 90.56Kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
3050Galvanised steel corrugated sheetsMaterialquintal19.026,105.001,16,117.10
1022Galvanised steel bolts & nuts 6 mm dia and 25 mmlong round head with slotsGalvanised steel bolts & nuts 6 mm dia and 25 mm long round head with slotsMaterial10 Nos88.438.003,359.20
1023Galvanised steel J or L hooks 8 mm diaMaterial10 Nos81130.0010,530.00
1207G.I. Limpet washerMaterial100 Nos16.9421.00355.74
1208Bitumen washerMaterial100 Nos16.9430.00508.20
9977Carriage of bolts and washersMaterialL.S.26.912.2761.09
9999SundriesMaterialL.S.53.822.27122.17
0130MistryLabourday1.3897.001,166.10
0112Carpenter 2nd classLabourday15.5816.0012,648.00
0114BeldarLabourday15.5736.0011,408.00
4202Red oxide Zinc chromate primerMateriallitre2.53140.00354.20
9977Carriage of materialMaterialL.S.0.522.271.18
0131PainterLabourday1.13816.00922.08
0115CoolieLabourday1.13736.00831.68
9999Brushes, sand papers i/c sundriesMaterialL.S.50.572.27114.79
0845Roofing paint for iron sheets in red colourMateriallitre3.75135.00506.25
9977Carriage of paintMaterialL.S.6.762.2715.35
0131PainterLabourday2.53816.002,064.48
0115CoolieLabourday2.53736.001,862.08
9999Brushes and SandpapersMaterialL.S.31.982.2772.59
9999SundriesMaterialL.S.38.092.2786.46
TOTAL
1,63,106.74
Add 1 % Water charges on “W”
1,631.07
TOTAL
1,64,737.81
Add GST on “X” (multiplying factor 0.2127)
35,039.73
TOTAL
1,99,777.54
Add 15% CPOH on “Y”
29,966.63
Add 15% CPOH on “Y”
2,29,744.17
Add Cess @ 1% on “Z”
2,297.44
Cost of 184.518 Sqm.
2,32,041.61
Cost of 1 Sqm.
1,257.56
Say
1,257.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 852. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works