Skip to main content

CPWD Analysis of Rates · Road Work

Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ±2%), Zinic+10% Al alloy+PVC coated, Mesh wire diameter 2.7/3.7mm (ID/OD), mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge

Item number
16.96
Priced inputs
5
Derived rate
4,882.20 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.96 Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ±2%), Zinic+10% Al alloy+PVC coated, Mesh wire diameter 2.7/3.7mm (ID/OD), mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge — is derived from 5 priced inputs and works out to ₹4,882.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Details cost of one Gabion box/Crates of
  • size 2mx1mx1m = 2 cum
  • Surface area required = 11.00 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
8578Crates made of Mesh type 10x12 (D=100 mm) Zn+10% Al alloy + PVC coated. Mesh wire diameter 2.70/3.70 mm (ID/OD)Crates made of Mesh type 10x12 (D=100 mm) Zn+10% Al alloy +PVC coated. Mesh wire diameter 2.70/3.70 mm (ID/OD).Materialsqm11320.003,520.00
7753Stone boulder with least dimension 200mmStone Boulder 50 mm to 200 mmMaterialcum2875.001,750.00
0128MateLabourday0.1816.0081.60
0125Mason (for plain stone work) 2nd classLabourday0.5816.00408.00
0114BeldarLabourday1.5736.001,104.00
TOTAL
6,863.60
Add 1 % Water charges on “W”
68.64
TOTAL
6,932.24
Add GST on “X” (multiplying factor 0.2127)
1,474.49
TOTAL
8,406.73
Add 15% CPOH on “Y”
1,261.01
TOTAL
9,667.74
Add Cess @ 1% on “Z”
96.68
Cost of 2 cum
9,764.42
Cost of 1 cum
4,882.21
Say
4,882.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1277. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works