Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ±2%), Zinic+10% Al alloy+PVC coated, Mesh wire diameter 2.7/3.7mm (ID/OD), mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge
- Item number
- 16.96
- Priced inputs
- 5
- Derived rate
- ₹4,882.20/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.96 (Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ±2%), Zinic+10% Al alloy+PVC coated, Mesh wire diameter 2.7/3.7mm (ID/OD), mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge) is derived from 5 priced inputs and works out to ₹4,882.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Details cost of one Gabion box/Crates of
- size 2mx1mx1m = 2 cum
- Surface area required = 11.00 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8578 | MAT | Crates made of Mesh type 10x12 (D=100 mm) Zn+10% Al alloy + PVC coated. Mesh wire diameter 2.70/3.70 mm (ID/OD)Crates made of Mesh type 10x12 (D=100 mm) Zn+10% Al alloy +PVC coated. Mesh wire diameter 2.70/3.70 mm (ID/OD). | sqm | 11 | 320.00 | 3,520.00 |
| 7753 | MAT | Stone boulder with least dimension 200mmStone Boulder 50 mm to 200 mm | cum | 2 | 875.00 | 1,750.00 |
| 0128 | LAB | Mate | day | 0.1 | 816.00 | 81.60 |
| 0125 | LAB | Mason (for plain stone work) 2nd class | day | 0.5 | 816.00 | 408.00 |
| 0114 | LAB | Beldar | day | 1.5 | 736.00 | 1,104.00 |
- TOTAL
- 6,863.60
- Add 1 % Water charges on “W”
- +68.64
- TOTAL
- 6,932.24
- Add GST on “X” (multiplying factor 0.2127)
- +1,474.49
- TOTAL
- 8,406.73
- Add 15% CPOH on “Y”
- +1,261.01
- TOTAL
- 9,667.74
- Add Cess @ 1% on “Z”
- +96.68
- Cost of 2 cum
- 9,764.42
- Cost of 1 cum
- 4,882.21
- SAY
- ₹4,882.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1277
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1277. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.