Providing and laying matt finished vitrified tile of size 300x300x9.8mm having with water absorption less than 0.5% and conforming to IS: 15622 of approved make in all colours and shades in for outdoor floors such as footpath, court yard, multi modals location etc., laid on 20mm thick base of cement mortar 1:4 (1 cement : 4 coarse sand) in all shapes & patterns including grouting the joints with white cement mixed with matching pigments etc. complete as per direction of Engineer-in-Charge
- Item number
- 16.89
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹1,455.65/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.89 (Providing and laying matt finished vitrified tile of size 300x300x9.8mm having with water absorption less than 0.5% and conforming to IS: 15622 of approved make in all colours and shades in for outdoor floors such as footpath, court yard, multi modals location etc., laid on 20mm thick base of cement mortar 1:4 (1 cement : 4 coarse sand) in all shapes & patterns including grouting the joints with white cement mixed with matching pigments etc. complete as per direction of Engineer-in-Charge) is derived from 8 priced inputs for 10 sqm and works out to ₹1,455.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Tile 300x300 x9.8mm = 10 sqm.
- LABOUR :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7896 | MAT | Vitrified tile | sqm | 10 | 495.00 | 4,950.00 |
| 9977 | MAT | Carriage | L.S. | 62.4 | 2.27 | 141.65 |
| SUB | Rate as per Item No.3.9 of SH: MORTARSRate as per item 3.9 | cum | 0.24 | 4,211.70 | 1,010.81 | |
| 9999 | MAT | Sundries | L.S. | 36.4 | 2.27 | 82.63 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.033 | 5,156.00 | 170.15 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 2 | 897.00 | 1,794.00 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 9999 | MAT | Sundries | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 10,232.10
- Add 1 % Water charges on “W”
- +102.32
- TOTAL
- 10,334.42
- Add GST on “X” (multiplying factor 0.2127)
- +2,198.13
- TOTAL
- 12,532.55
- Add 15% CPOH on “Y”
- +1,879.88
- TOTAL
- 14,412.43
- Add Cess @ 1% on “Z”
- +144.12
- Cost for 10 sqm.
- 14,556.55
- Rate per sqm.
- 1,455.66
- SAY
- ₹1,455.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1272
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1272. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.