Providing and laying matt finished vitrified tile of size 100x100x16mm having water absorption less than 0.5% and conforming to IS: 15622 of approved make in all colours and shades in out door floors such as footpath, court yard multi models etc., laid on 20mm thick base of cement mortar 1:4 (1cement : 4 coarse sand) in all shapes & patterns including grouting the joints with white cement mixed with matching pigments etc. complete as direction of Engineer-in-Charge
- Item number
- 16.88
- Analysis basis
- Detail of cost for 10 sqm.
- Priced inputs
- 8
- Derived rate
- ₹2,159.85 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.88 — Providing and laying matt finished vitrified tile of size 100x100x16mm having water absorption less than 0.5% and conforming to IS: 15622 of approved make in all colours and shades in out door floors such as footpath, court yard multi models etc., laid on 20mm thick base of cement mortar 1:4 (1cement : 4 coarse sand) in all shapes & patterns including grouting the joints with white cement mixed with matching pigments etc. complete as direction of Engineer-in-Charge — is derived from 8 priced inputs for 10 sqm and works out to ₹2,159.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Matt finished vitrified tile 100x100 x16mm
- LABOUR :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7895 | Matt finished vitrified tile 100x100 x16mmMatt finished vitrified tile 100x100 x16 mmMaterial | sqm | 10 | 990.00 | 9,900.00 |
| 9977 | CarriageMaterial | L.S. | 62.4 | 2.27 | 141.65 |
| Rate as per Item No.3.9 of SH: MORTARSRate as per item 3.9Sub-analysis | cum | 0.24 | 4,211.70 | 1,010.81 | |
| 9999 | SundriesMaterial | L.S. | 36.4 | 2.27 | 82.63 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.033 | 5,156.00 | 170.15 |
| 0123 | Mason 1st classMason 1st classLabour | day | 2 | 897.00 | 1,794.00 |
| 0115 | CoolieLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | SundriesMaterial | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 15,182.10
- Add 1 % Water charges on “W”
- 151.82
- TOTAL
- 15,333.92
- Add GST on “X” (multiplying factor 0.2127)
- 3,261.52
- TOTAL
- 18,595.44
- Add 15% CPOH on “Y”
- 2,789.32
- TOTAL
- 21,384.76
- Add Cess @ 1% on “Z”
- 213.85
- Cost for 10 sqm.
- 21,598.61
- Cost per sqm.
- 2,159.86
- Say
- 2,159.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1271. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate