CPWD Analysis of Rates · Road Work

Providing and laying matt finished vitrified tile of size 100x100x16mm having water absorption less than 0.5% and conforming to IS: 15622 of approved make in all colours and shades in out door floors such as footpath, court yard multi models etc., laid on 20mm thick base of cement mortar 1:4 (1cement : 4 coarse sand) in all shapes & patterns including grouting the joints with white cement mixed with matching pigments etc. complete as direction of Engineer-in-Charge

Item number
16.88
Analysis basis
Detail of cost for 10 sqm.
Priced inputs
8
Derived rate
2,159.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.88 Providing and laying matt finished vitrified tile of size 100x100x16mm having water absorption less than 0.5% and conforming to IS: 15622 of approved make in all colours and shades in out door floors such as footpath, court yard multi models etc., laid on 20mm thick base of cement mortar 1:4 (1cement : 4 coarse sand) in all shapes & patterns including grouting the joints with white cement mixed with matching pigments etc. complete as direction of Engineer-in-Charge — is derived from 8 priced inputs for 10 sqm and works out to ₹2,159.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Matt finished vitrified tile 100x100 x16mm
  • LABOUR :
CodeInputUnitQuantityRate (INR)Amount (INR)
7895Matt finished vitrified tile 100x100 x16mmMatt finished vitrified tile 100x100 x16 mmMaterialsqm10990.009,900.00
9977CarriageMaterialL.S.62.42.27141.65
Rate as per Item No.3.9 of SH: MORTARSRate as per item 3.9Sub-analysiscum0.244,211.701,010.81
9999SundriesMaterialL.S.36.42.2782.63
0367Portland Cement (OPC-43 grade)Materialtonne0.0335,156.00170.15
0123Mason 1st classMason 1st classLabourday2897.001,794.00
0115CoolieLabourday2736.001,472.00
9999SundriesMaterialL.S.269.12.27610.86
TOTAL
15,182.10
Add 1 % Water charges on “W”
151.82
TOTAL
15,333.92
Add GST on “X” (multiplying factor 0.2127)
3,261.52
TOTAL
18,595.44
Add 15% CPOH on “Y”
2,789.32
TOTAL
21,384.76
Add Cess @ 1% on “Z”
213.85
Cost for 10 sqm.
21,598.61
Cost per sqm.
2,159.86
Say
2,159.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1271. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.