CPWD Analysis of Rates · Road Work
Annexure ‘B’ to Item number 16.43 (steel form work for concrete)
- Item number
- 16.43B
- Analysis basis
- Details of cost for 85.00 cum concrete
- Priced inputs
- 4
- Derived rate
- ₹1,046.90 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.43B — Annexure ‘B’ to Item number 16.43 (steel form work for concrete) — is derived from 4 priced inputs for 85.00 cum and works out to ₹1,046.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- ANALYSIS OF ANNEXTURE ‘B’ 16.43B
- (Required in 16.43)
- STEEL FORM WORK :
- Part-I Cost of materials :
- Assuming that pavement 30m long 22.5m
- wide and 0.30m deep having panel size
- 6.15x4.61x0.30m or 8.50cu. laid in a day of
- 8 hrs. Hence form work to be provided for 2
- days.
- Channel ISJC 300 for 50 slab of size
- 6.15mx4.61m=22x30.75+2x46.10 =768.70
- m
- Total for 500 slabs = 768.70mx10=7687.00
- m
- 7687 m @ 33.10 kg/ m = 254440 kg =
- 2544.40 q
- Assuming that channel will become
- unserviceable after use for 5000 slab (100
- times) and salvage value of steel shall fetch
- 20% of its basic cost. Qty for using once
- =2544.40*0.80/5000= 0.407q
- Part-II Labour for assembling, errection,
- dismeritelling and cleaning the shuttering.
- Assuming that 255 labour for steel
- shuttering shall be required as compared to
- timber shuttering. Contact area of 50 slabs
- of steel shuttering.
- Long channel = 11x20x0.30 = 66.00
- = 2x45.10x0.30 = 27.06
- Total for 500 slabs= 93.06x10=930.60
- Carriage of steel for extra lead of runway
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1007 | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterial | quintal | 0.407 | 5,965.00 | 2,427.76 |
| 0103 | Blacksmith 2nd classLabour | day | 28.6 | 816.00 | 23,337.60 |
| 0114 | BeldarLabour | day | 28.6 | 736.00 | 21,049.60 |
| 0114 | BeldarLabour | day | 57.3 | 736.00 | 42,172.80 |
- TOTAL
- 88,987.76
- Cost for 85.00 cum
- 88,987.76
- Cost of steel form work per cum.
- 1,046.91
- Say
- 1,046.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1209. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.