Analysis basis
85.00 cum
Priced inputs
4
Derived rate
₹1,046.90/ CUM
D-01/RATE ANALYSISITEM 16.43B

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.43B (Annexure ‘B’ to Item number 16.43 (steel form work for concrete)) is derived from 4 priced inputs for 85.00 cum and works out to ₹1,046.90 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • ANALYSIS OF ANNEXTURE ‘B’ 16.43B
  • (Required in 16.43)
  • STEEL FORM WORK :
  • Part-I Cost of materials :
  • Assuming that pavement 30m long 22.5m
  • wide and 0.30m deep having panel size
  • 6.15x4.61x0.30m or 8.50cu. laid in a day of
  • 8 hrs. Hence form work to be provided for 2
  • days.
  • Channel ISJC 300 for 50 slab of size
  • 6.15mx4.61m=22x30.75+2x46.10 =768.70
  • m
  • Total for 500 slabs = 768.70mx10=7687.00
  • m
  • 7687 m @ 33.10 kg/ m = 254440 kg =
  • 2544.40 q
  • Assuming that channel will become
  • unserviceable after use for 5000 slab (100
  • times) and salvage value of steel shall fetch
  • 20% of its basic cost. Qty for using once
  • =2544.40*0.80/5000= 0.407q
  • Part-II Labour for assembling, errection,
  • dismeritelling and cleaning the shuttering.
  • Assuming that 255 labour for steel
  • shuttering shall be required as compared to
  • timber shuttering. Contact area of 50 slabs
  • of steel shuttering.
  • Long channel = 11x20x0.30 = 66.00
  • = 2x45.10x0.30 = 27.06
  • Total for 500 slabs= 93.06x10=930.60
  • Carriage of steel for extra lead of runway
ANALYSIS OF RATES · ITEM 16.43BDETAILS OF COST FOR 85.00 CUM CONCRETE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal0.4075,965.002,427.76
0103LABBlacksmith 2nd classday28.6816.0023,337.60
0114LABBeldarday28.6736.0021,049.60
0114LABBeldarday57.3736.0042,172.80
BUILD-UP TO RATE
TOTAL
88,987.76
Cost for 85.00 cum
88,987.76
Cost of steel form work per cum.
1,046.91
SAY
₹1,046.90
D-02/SOURCEPRINTED PAGE 1209
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1209

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1209. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.