CPWD Analysis of Rates · Road Work
Providing and laying design mix cement concrete of M-30 grade, in roads/ taxi tracks/ runways, using cement content as per design mix, using coarse sand and graded stone aggregate of 40 mm nominal size in appropriate proportions as per approved & specified design criteria, providing dowel bars with sleeve/ tie bars wherever required, laying at site, spreading and compacting mechanically by using needle and surface vibrators, levelling to required slope/ camber, finishing with required texture, including steel form work with sturdy M.S. channel sections, curing, making provision for contraction/ expansion, construction & longitudinal joints (10 mm wide x 50 mm deep) by groove cutting machine, providing and filling joints with approved joint filler and sealants, complete all as per direction of Engineer-in-charge (Item of joint fillers, sealants, dowel bars with sleeve/ tie bars to be paid separately). Note:- Cement content considered in M-30 is @ 340 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately
Cement concrete manufactured in automatic batching plant (RMC plant) i/c transportation to site in transit mixer
- Item number
- 16.43.2
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 19
- Derived rate
- ₹11,098.45 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.43.2 — Providing and laying design mix cement concrete of M-30 grade, in roads/ taxi tracks/ runways, using cement content as per design mix, using coarse sand and graded stone aggregate of 40 mm nominal size in appropriate proportions as per approved & specified design criteria, providing dowel bars with sleeve/ tie bars wherever required, laying at site, spreading and compacting mechanically by using needle and surface vibrators, levelling to required slope/ camber, finishing with required texture, including steel form work with sturdy M.S. channel sections, curing, making provision for contraction/ expansion, construction & longitudinal joints (10 mm wide x 50 mm deep) by groove cutting machine, providing and filling joints with approved joint filler and sealants, complete all as per direction of Engineer-in-charge (Item of joint fillers, sealants, dowel bars with sleeve/ tie bars to be paid separately). Note:- Cement content considered in M-30 is @ 340 kg/cum. Excess/ less cement used as per design mix is payable/ recoverable separately Cement concrete manufactured in automatic batching plant (RMC plant) i/c transportation to site in transit mixer — is derived from 19 priced inputs for 1 cum and works out to ₹11,098.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- LABOUR :- FOR MIXING AND LAYING
- For compaction by vibrator
- (Assuming 25 cum. per day)
- (SHP) with 50 cum. output per day
- with 25 cum. output per day
- Add for steel form work
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.34 | 5,156.00 | 1,753.04 |
| 0293 | Stone Aggregate (Single size) : 40 mm nominal sizeMaterial | cum | 0.52 | 1,400.00 | 728.00 |
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 0.22 | 1,425.00 | 313.50 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 0.11 | 1,400.00 | 154.00 |
| 0982 | Coarse sand (zone III)Material | cum | 0.445 | 1,450.00 | 645.25 |
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.05 | 897.00 | 44.85 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.05 | 816.00 | 40.80 |
| 0128 | MateLabour | day | 0.04 | 816.00 | 32.64 |
| 0155 | Mason (average)Labour | day | 0.07 | 857.00 | 59.99 |
| 0114 | BeldarLabour | day | 0.07 | 736.00 | 51.52 |
| 0004 | Production cost of concrete by batch mix plantMachinery | cum | 1 | 450.00 | 450.00 |
| 0029 | Carriage of concrete by transit mixer.Carriage of ready mixed concrete by rotatory transit mixerMachinery | km/ cum | 10 | 40.00 | 400.00 |
| 0009 | Pumping charges of concrete including Hire charges of pump, piping work & accessories etcPumping charges of concrete including Hire charges of pump, piping work & accessories etc.Machinery | cum | 1 | 250.00 | 250.00 |
| 0021 | Pin vibratorMachinery | day | 0.025 | 300.00 | 7.50 |
| 0022 | Surface VibratorMachinery | day | 0.05 | 350.00 | 17.50 |
| Rate as per Item Number 16.43B of SH: Road workRate as per item 16.43BSub-analysis | cum | 1 | 1,046.90 | 1,046.90 | |
| 9999 | Cutting and making jointsMaterial | L.S. | 50 | 2.27 | 113.50 |
- TOTAL
- 7,801.31
- Add 1 % Water charges on “W”
- 78.01
- TOTAL
- 7,879.32
- Add GST on “X” (multiplying factor 0.2127)
- 1,675.93
- TOTAL
- 9,555.25
- Add 15% CPOH on “Y”
- 1,433.29
- TOTAL
- 10,988.54
- Add Cess @ 1% on “Z”
- 109.89
- Cost per cum.
- 11,098.43
- Say
- 11,098.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1208. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.