Supplying and stacking at site
- Item number
- 16.3.5
- Analysis basis
- 1 cum
- Priced inputs
- 1
- Derived rate
- ₹872.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.5 (Supplying and stacking at site Over burnt (Jhama) brick aggregate 90 mm to 45 mm) is derived from 1 priced inputs for 1 cum and works out to ₹872.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2909 | MAT | Over burnt (Jhama) Brick Aggregate: 90 mm to 40 mm size | cum | 1 | 613.00 | 613.00 |
- TOTAL
- 613.00
- Add 1 % Water charges on "W"
- +6.13
- TOTAL
- 619.13
- Add GST on "X" (multiplying factor 0.2127)
- +131.69
- TOTAL
- 750.82
- Add 15% CPOH on "Y"
- +112.62
- TOTAL
- 863.44
- Add Cess @ 1% on "Z"
- +8.63
- Cost for 1 cum
- 872.07
- SAY
- ₹872.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1147
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1147. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.