CPWD Analysis of Rates · Road Work

Supplying and stacking at site

Over burnt (Jhama) brick aggregate 90 mm to 45 mm

Item number
16.3.5
Analysis basis
Details of cost for 1 cum.
Priced inputs
1
Derived rate
872.05 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.5 Supplying and stacking at site Over burnt (Jhama) brick aggregate 90 mm to 45 mm — is derived from 1 priced inputs for 1 cum and works out to ₹872.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
2909Over burnt (Jhama) Brick Aggregate: 90 mm to 40 mm sizeMaterialcum1613.00613.00
TOTAL
613.00
Add 1 % Water charges on "W"
6.13
TOTAL
619.13
Add GST on "X" (multiplying factor 0.2127)
131.69
TOTAL
750.82
Add 15% CPOH on "Y"
112.62
TOTAL
863.44
Add Cess @ 1% on "Z"
8.63
Cost for 1 cum
872.07
Say
872.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1147. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.