CPWD Analysis of Rates · Road Work

Welded steel wire fabric fencing with posts of specified material and of standard design placed and embedded in cement concrete blocks 45x45x 60 cm of mix 1:5:10 (1 cement:5 fine sand : 10 graded stone aggregate 40 mm nominal size), every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and struts embedded in cement concrete blocks 70x45x50 cm of the same mix, provided with welded steel wire fabric fixed between the posts fitted and fixed with G.I. staples on wooden plugs or tied to 6 mm bar nibs with G.I. binding wire (cost of posts, welded steel wire fabric, painting, earth work in excavation and concrete to be paid for separately)

Item number
16.20
Analysis basis
Details of cost for 30 metres i.e.30x1.20
Priced inputs
7
Derived rate
66.15 / metres

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.20 Welded steel wire fabric fencing with posts of specified material and of standard design placed and embedded in cement concrete blocks 45x45x 60 cm of mix 1:5:10 (1 cement:5 fine sand : 10 graded stone aggregate 40 mm nominal size), every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and struts embedded in cement concrete blocks 70x45x50 cm of the same mix, provided with welded steel wire fabric fixed between the posts fitted and fixed with G.I. staples on wooden plugs or tied to 6 mm bar nibs with G.I. binding wire (cost of posts, welded steel wire fabric, painting, earth work in excavation and concrete to be paid for separately) — is derived from 7 priced inputs for 30 metres and works out to ₹66.15 per metres after water charges, GST, CPOH and cess. The full build-up is below.

  • =36.00sqm
  • Labour for fixing posts in line fixing and
  • stretching - welded wire fabric :
CodeInputUnitQuantityRate (INR)Amount (INR)
0123Mason 1st classMason 1st classLabourday0.12897.00107.64
0124Mason 2nd classMason 2nd classLabourday0.12816.0097.92
0114BeldarLabourday0.5736.00368.00
0102Blacksmith 1st classLabourday0.5897.00448.50
0103Blacksmith 2nd classLabourday0.5816.00408.00
9999G.I. staple or binding wireMaterialL.S.53.822.27122.17
9999SundriesMaterialL.S.53.822.27122.17
TOTAL
1,674.40
Add 1 % Water charges on “W”
16.74
TOTAL
1,691.14
Add GST on “X” (multiplying factor 0.2127)
359.71
TOTAL
2,050.85
Add 15% CPOH on “Y”
307.63
TOTAL
2,358.48
Add Cess @ 1% on “Z”
23.58
Cost for 36 sqm
2,382.06
Cost per sqm
66.17
Say
66.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1163. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.