CPWD Analysis of Rates · Road Work
Welded steel wire fabric fencing with posts of specified material and of standard design placed and embedded in cement concrete blocks 45x45x 60 cm of mix 1:5:10 (1 cement:5 fine sand : 10 graded stone aggregate 40 mm nominal size), every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and struts embedded in cement concrete blocks 70x45x50 cm of the same mix, provided with welded steel wire fabric fixed between the posts fitted and fixed with G.I. staples on wooden plugs or tied to 6 mm bar nibs with G.I. binding wire (cost of posts, welded steel wire fabric, painting, earth work in excavation and concrete to be paid for separately)
- Item number
- 16.20
- Analysis basis
- Details of cost for 30 metres i.e.30x1.20
- Priced inputs
- 7
- Derived rate
- ₹66.15 / metres
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.20 — Welded steel wire fabric fencing with posts of specified material and of standard design placed and embedded in cement concrete blocks 45x45x 60 cm of mix 1:5:10 (1 cement:5 fine sand : 10 graded stone aggregate 40 mm nominal size), every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and struts embedded in cement concrete blocks 70x45x50 cm of the same mix, provided with welded steel wire fabric fixed between the posts fitted and fixed with G.I. staples on wooden plugs or tied to 6 mm bar nibs with G.I. binding wire (cost of posts, welded steel wire fabric, painting, earth work in excavation and concrete to be paid for separately) — is derived from 7 priced inputs for 30 metres and works out to ₹66.15 per metres after water charges, GST, CPOH and cess. The full build-up is below.
- =36.00sqm
- Labour for fixing posts in line fixing and
- stretching - welded wire fabric :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0123 | Mason 1st classMason 1st classLabour | day | 0.12 | 897.00 | 107.64 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.12 | 816.00 | 97.92 |
| 0114 | BeldarLabour | day | 0.5 | 736.00 | 368.00 |
| 0102 | Blacksmith 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0103 | Blacksmith 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 9999 | G.I. staple or binding wireMaterial | L.S. | 53.82 | 2.27 | 122.17 |
| 9999 | SundriesMaterial | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 1,674.40
- Add 1 % Water charges on “W”
- 16.74
- TOTAL
- 1,691.14
- Add GST on “X” (multiplying factor 0.2127)
- 359.71
- TOTAL
- 2,050.85
- Add 15% CPOH on “Y”
- 307.63
- TOTAL
- 2,358.48
- Add Cess @ 1% on “Z”
- 23.58
- Cost for 36 sqm
- 2,382.06
- Cost per sqm
- 66.17
- Say
- 66.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1163. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works