Skip to main content

CPWD Analysis of Rates · Repairs to Buildings

Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5 sqm and under, including cutting the patch in proper shape, raking out joints and preparing plastering the wall surface with white cement based polymer modified self curing mortar, including disposal of rubbish, all complete as per the direction of Engineer-In-Charge

Item number
14.75
Analysis basis
Details of cost for 10 sqm
Priced inputs
6
Derived rate
670.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.75 Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5 sqm and under, including cutting the patch in proper shape, raking out joints and preparing plastering the wall surface with white cement based polymer modified self curing mortar, including disposal of rubbish, all complete as per the direction of Engineer-In-Charge — is derived from 6 priced inputs for 10 sqm and works out to ₹670.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • i/c 2% wastage
CodeInputUnitQuantityRate (INR)Amount (INR)
0772White cement based polymer modified self curing compound in powder formMaterialkg12518.002,250.00
9977Carriage of white cement based polymer modified self curing compound in powder formMaterialL.S.21.12.2747.90
0155Mason (average)Labourday1.21857.001,036.97
0114BeldarLabourday0.54736.00397.44
0115CoolieLabourday1.29736.00949.44
9999Scaffolding and sunderiesMaterialL.S.15.212.2734.53
TOTAL
4,716.28
Add 1 % Water charges on “W”
47.16
TOTAL
4,763.44
Add GST on “X” (multiplying factor 0.2127)
1,013.18
TOTAL
5,776.62
Add 15% CPOH on “Y”
866.49
TOTAL
6,643.11
Add Cess @ 1% on “Z”
66.43
Cost of 10 sqm
6,709.54
Cost of 1 sqm
670.95
Say
670.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1082. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works