Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5 sqm and under, including cutting the patch in proper shape, raking out joints and preparing plastering the wall surface with white cement based polymer modified self curing mortar, including disposal of rubbish, all complete as per the direction of Engineer-In-Charge

Item number
14.75
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹670.95/ SQM
D-01/RATE ANALYSISITEM 14.75

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.75 (Repair to plaster of thickness 12mm to 20 mm in patches of area 2.5 sqm and under, including cutting the patch in proper shape, raking out joints and preparing plastering the wall surface with white cement based polymer modified self curing mortar, including disposal of rubbish, all complete as per the direction of Engineer-In-Charge) is derived from 6 priced inputs for 10 sqm and works out to ₹670.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • i/c 2% wastage
ANALYSIS OF RATES · ITEM 14.75DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0772MATWhite cement based polymer modified self curing compound in powder formkg12518.002,250.00
9977MATCarriage of white cement based polymer modified self curing compound in powder formL.S.21.12.2747.90
0155LABMason (average)day1.21857.001,036.97
0114LABBeldarday0.54736.00397.44
0115LABCoolieday1.29736.00949.44
9999MATScaffolding and sunderiesL.S.15.212.2734.53
BUILD-UP TO RATE
TOTAL
4,716.28
Add 1 % Water charges on “W”
+47.16
TOTAL
4,763.44
Add GST on “X” (multiplying factor 0.2127)
+1,013.18
TOTAL
5,776.62
Add 15% CPOH on “Y”
+866.49
TOTAL
6,643.11
Add Cess @ 1% on “Z”
+66.43
Cost of 10 sqm
6,709.54
Cost of 1 sqm
670.95
SAY
₹670.95
D-02/SOURCEPRINTED PAGE 1082
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1082

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1082. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.