Providing and fixing 14 mm bright finished brass spring catch to steel centre hung ventilators with necessary welding and machine screws etc. complete

Item number
14.74
Analysis basis
10 nos
Priced inputs
3
Derived rate
₹68.35/ NOS
D-01/RATE ANALYSISITEM 14.74

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.74 (Providing and fixing 14 mm bright finished brass spring catch to steel centre hung ventilators with necessary welding and machine screws etc. complete) is derived from 3 priced inputs for 10 nos and works out to ₹68.35 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 14.74DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0428MATBrass fanlight catch10 Nos1187.00187.00
9999MATFixing charges including welding and materials etcL.S.125.582.27285.07
9977MATCarriage of materialsL.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
480.33
Add 1 % Water charges on “W”
+4.80
TOTAL
485.13
Add GST on “X” (multiplying factor 0.2127)
+103.19
TOTAL
588.32
Add 15% CPOH on “Y”
+88.25
TOTAL
676.57
Add Cess @ 1% on “Z”
+6.77
Cost of 10 window fasteners
683.34
Cost of each
68.33
SAY
₹68.35
D-02/SOURCEPRINTED PAGE 1082
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1082

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1082. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS