CPWD Analysis of Rates · Repairs to Buildings

Scaffolding

Item number
14.72X
Analysis basis
Details of cost for area 22.5 x 9.0= 202.50
Priced inputs
7
Derived rate
9,081.00 / area 22

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.72X Scaffolding — is derived from 7 priced inputs for area 22 and works out to ₹9,081.00 per area 22 after water charges, GST, CPOH and cess. The full build-up is below.

  • sqm
  • Assuming shuttering material will become
  • unserviceable after use of 40 times
  • 7x2=14 nos
  • 40mm dia M.S. Tube
  • Vertical standard 2.5m length
  • = 7x2x9x2.5 = 315.00 m
  • Bracing ledder 1.5m length = 7x2x9x4.0873 =
  • 513.00 m
  • Side support 6.00m length = 3x2x6.00= 36.00 m
  • Horizontal support 3.00m length = 18x3x3.00
  • = 162.00 m
  • Total = 1026.00m @ 3.67 kg/m = 3765.42 kg
  • 7x2x9 = 126 nos x 0.40m length = 50.40m
  • 50.40m @ 2.46kg/m = 123.98kg
  • 2x7x2x9 = 252 nos @ 0.15 kg each
  • = 37.80 kg = 0.378 q
  • 2x3x2 + 2x18x3 = 120 nos
  • 3 nos x 18 lines = 54 nos
  • Two level plate challies = 2x 18 lines = 36
  • nos, Total = 90 nos
  • Vertical standards 5x7x2x9 = 630.00 Nos.
  • 2x18x19 = 684 Nos.
  • Total =1314 Nos.
  • Considering that scaffolding shall be
  • unserviceable after using 40 times
CodeInputUnitQuantityRate (INR)Amount (INR)
7397Base jackMaterialeach14155.002,170.00
4009Mild steel tubes hot finished welded typeMaterialkilogram3,765.4272.002,71,110.24
7387Spigot for standard jointingMaterialkg123.9844.005,455.12
1034Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterialquintal0.3785,200.001,965.60
7346Double couplerMaterialeach12049.005,880.00
7398ChalliesMaterialeach90834.0075,060.00
7399Cup lockCup locksMaterialeach1,31450.0065,700.00
TOTAL
4,27,340.96
Add 10% for maintenance on P
42,734.10
Less 25% salvage value on P
-1,06,835.24
TOTAL (P+Q+R)
3,63,239.82
cost of using once
9,081.00
Say
9,081.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1081. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.