CPWD Analysis of Rates · Repairs to Buildings

Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. Note: - This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done

Item number
14.72
Analysis basis
Details of cost for area 22.5m x 9.0m =202.5
Priced inputs
4
Derived rate
338.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.72 Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. Note: - This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done — is derived from 4 priced inputs for area 22 and works out to ₹338.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.14.72X of SH:Repairs to BuildingsRate as per item 14.72XSub-analysiseach19,081.009,081.00
0116Fitter (grade 1)Labourday15.5897.0013,903.50
0114BeldarLabourday31736.0022,816.00
9999SundriesMaterialL.S.1,0352.272,349.45
TOTAL
48,149.95
Add 1 % Water charges on “W”
481.50
TOTAL
48,631.45
Add GST on “X” (multiplying factor 0.2127)
10,343.91
TOTAL
58,975.36
Add 15% CPOH on “Y”
8,846.30
TOTAL
67,821.66
Add Cess @ 1% on “Z”
678.22
Cost of 202.50 sqm.
68,499.88
Cost of 1 sqm.
338.27
Say
338.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1080. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.