Providing and fixing bright finished brass hard drawn hooks and eyes

100 mm
Item number
14.35.5
Analysis basis
10 nos
Priced inputs
3
Derived rate
₹61.85/ NOS
D-01/RATE ANALYSISITEM 14.35.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.35.5 (Providing and fixing bright finished brass hard drawn hooks and eyes : 100 mm) is derived from 3 priced inputs for 10 nos and works out to ₹61.85 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 14.35.5DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0422MATBrass hard drawn hooks and eyes 100 mm10 Nos1379.00379.00
9977MATCarriage of materialL.S.0.912.272.07
0111LABCarpenter 1st classday0.06897.0053.82
BUILD-UP TO RATE
TOTAL
434.89
Add 1 % Water charges on “W”
+4.35
TOTAL
439.24
Add GST on “X” (multiplying factor 0.2127)
+93.43
TOTAL
532.67
Add 15% CPOH on “Y”
+79.90
TOTAL
612.57
Add Cess @ 1% on “Z”
+6.13
Cost of 10 Nos
618.70
Cost of each
61.87
SAY
₹61.85
D-02/SOURCEPRINTED PAGE 1075
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1075

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1075. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.