Providing and fixing M.S. round or square bars with M.S. flats at required spacing in wooden frames of windows and clerestory windows

Item number
14.29
Analysis basis
33.67 kg
Priced inputs
6
Derived rate
₹120.75/ KG
D-01/RATE ANALYSISITEM 14.29

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.29 (Providing and fixing M.S. round or square bars with M.S. flats at required spacing in wooden frames of windows and clerestory windows) is derived from 6 priced inputs for 33.67 kg and works out to ₹120.75 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • M.S. bar 16 mm dia 13x136 cm = 17.68 m @
  • 1.58 kg/m = 27.93 kg
  • Total = 30.72 kg or 0.307 q
  • M.S. flat 40x6mm 2x96cm = 192cm+
  • 1x110cm = 110cm
  • = 302cm+
  • Total = 332cm.@ 1.90 kg/m = 6.31 kg
  • Add for wastage @ 10% =2.79 kg
  • Add wastage @ 10% = 30cm
  • Say 0.063 q
ANALYSIS OF RATES · ITEM 14.29DETAILS OF COST FOR WINDOW -140X110CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1003MATMild steel round bar above 12 mm diaquintal0.3075,450.001,673.15
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.0635,450.00343.35
9999MATSundriesL.S.26.912.2761.09
0103LABBlacksmith 2nd classday0.35816.00285.60
0112LABCarpenter 2nd classday0.2816.00163.20
0114LABBeldarday0.45736.00331.20
BUILD-UP TO RATE
TOTAL
2,857.59
Add 1 % Water charges on “W”
+28.58
TOTAL
2,886.17
Add GST on “X” (multiplying factor 0.2127)
+613.89
TOTAL
3,500.06
Add 15% CPOH on “Y”
+525.01
TOTAL
4,025.07
Add Cess @ 1% on “Z”
+40.25
Cost of 33.67 kg.(5.74+27.93=33.67kg)
4,065.32
Cost of 1 kg.
120.74
SAY
₹120.75
D-02/SOURCEPRINTED PAGE 1068
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1068

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1068. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.