CPWD Analysis of Rates · Repairs to Buildings

Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting masonry for holdfasts, embedding hold fasts in cement concrete blocks of size 15 x 10 x 10 cm with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size), painting two coats of approved wood preservative to sides of chowkhats and making good the damages to walls and floors as required complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge

Clerestory window chowkhats

Item number
14.2.3
Analysis basis
Detail of cost for 10 Nos.
Priced inputs
19
Derived rate
851.00 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.2.3 Fixing chowkhats in existing opening including embedding chowkhats in floors or walls cutting masonry for holdfasts, embedding hold fasts in cement concrete blocks of size 15 x 10 x 10 cm with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size), painting two coats of approved wood preservative to sides of chowkhats and making good the damages to walls and floors as required complete, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge Clerestory window chowkhats — is derived from 19 priced inputs for 10 Nos and works out to ₹851.00 each after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 6 (1 cement : 6 fine sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.071,425.0099.75
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0241,400.0033.60
0982Coarse sand (zone III)Materialcum0.0471,450.0068.15
0367Portland Cement (OPC-43 grade)Materialtonne0.0225,156.00113.43
0114BeldarLabourday0.09736.0066.24
0115CoolieLabourday0.065736.0047.84
0130MistryLabourday0.028897.0025.12
0123Mason 1st classMason 1st classLabourday0.006897.005.38
0124Mason 2nd classMason 2nd classLabourday0.006816.004.90
0128MateLabourday0.004816.003.26
9999Scaffolding and sundriesMaterialL.S.5.22.2711.80
9999Hire and running charges of mechanical mixerMaterialL.S.2.62.275.90
9999SundriesMaterialL.S.1.32.272.95
Rate as per Item Number 3.6 of SH: MortarsRate as per item 3.6Sub-analysiscum0.033,038.5091.16
9999Cement concrete 1:2:4 filled in chase cutMaterialL.S.80.62.27182.96
9999Painting two coats of coaltarMaterialL.S.9.12.2720.66
0155Mason (average)Labourday1.7857.001,456.90
0114BeldarLabourday5736.003,680.00
9999SundriesMaterialL.S.27.32.2761.97
TOTAL
5,981.97
Add 1 % Water charges on “W”
59.82
TOTAL
6,041.79
Add GST on “X” (multiplying factor 0.2127)
1,285.09
TOTAL
7,326.88
Add 15% CPOH on “Y”
1,099.03
TOTAL
8,425.91
Add Cess @ 1% on “Z”
84.26
Cost of 10 Nos.
8,510.17
Cost of each
851.02
Say
851.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1041. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.