CPWD Analysis of Rates · Repairs to Buildings
Refixing old glass panes with putty and nails
- Item number
- 14.10
- Analysis basis
- Details of cost for 1 sqm
- Priced inputs
- 6
- Derived rate
- ₹729.85 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.10 — Refixing old glass panes with putty and nails — is derived from 6 priced inputs for 1 sqm and works out to ₹729.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0863 | Putty for wood workMaterial | kilogram | 0.68 | 32.00 | 21.76 |
| 9999 | SpiritMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | NailsMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 0119 | GlazierLabour | day | 0.3 | 816.00 | 244.80 |
| 0114 | BeldarLabour | day | 0.3 | 736.00 | 220.80 |
| 9999 | SundriesMaterial | L.S. | 1.43 | 2.27 | 3.25 |
- TOTAL
- 513.04
- Add 1 % Water charges on “W”
- 5.13
- TOTAL
- 518.17
- Add GST on “X” (multiplying factor 0.2127)
- 110.21
- TOTAL
- 628.38
- Add 15% CPOH on “Y”
- 94.26
- TOTAL
- 722.64
- Add Cess @ 1% on “Z”
- 7.23
- Add 15 % Contractor’s profit and overheads
- 729.87
- Cost of 1.00 sqm
- 729.87
- Say
- 729.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1047. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works