Providing and laying reinforced cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)

Item number
5.4A
Analysis basis
1 cum
Priced inputs
6
Derived rate
₹8,650.85/ CUM
D-01/RATE ANALYSISITEM 5.4A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.4A (Providing and laying reinforced cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)) is derived from 6 priced inputs for 1 cum and works out to ₹8,650.85 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • Cement concrete 1:1.5:3
  • LABOUR:
  • Extra labour for laying CC in RCC work
ANALYSIS OF RATES · ITEM 5.4ADETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1cum18,170.058,170.05
0114LABBeldarday0.1736.0073.60
0101LABBhistiday0.2816.00163.20
0123LABMason 1st classMason 1st classday0.04897.0035.88
0124LABMason 2nd classMason 2nd classday0.04816.0032.64
0128LABMateday0.04816.0032.64
BUILD-UP TO RATE
Total
8,508.01
Add 1 % Water charges on “W-A”
+3.38
TOTAL
8,511.39
Add GST on “X-A” (multiplying factor 0.2127)
+72.60
TOTAL
8,583.99
Add 15% CPOH on “Y-A”
+62.09
TOTAL
8,646.08
Add Cess @ 1% on “Z-A”
+4.76
Cost of 1 cum
8,650.84
SAY
₹8,650.85
D-02/SOURCEPRINTED PAGE 211
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
211

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 211. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.