CPWD Analysis of Rates · Reinforced Cement Concrete
Providing and laying reinforced cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
- Item number
- 5.4A
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 6
- Derived rate
- ₹8,650.85 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.4A — Providing and laying reinforced cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand Including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%) — is derived from 6 priced inputs for 1 cum and works out to ₹8,650.85 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- Cement concrete 1:1.5:3
- LABOUR:
- Extra labour for laying CC in RCC work
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Sub AR-1 (Ref item no 4.1.2)Rate as per item Sub AR-1Sub-analysis | cum | 1 | 8,170.05 | 8,170.05 | |
| 0114 | BeldarLabour | day | 0.1 | 736.00 | 73.60 |
| 0101 | BhistiLabour | day | 0.2 | 816.00 | 163.20 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.04 | 897.00 | 35.88 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.04 | 816.00 | 32.64 |
| 0128 | MateLabour | day | 0.04 | 816.00 | 32.64 |
- Total
- 8,508.01
- Add 1 % Water charges on “W-A”
- 3.38
- TOTAL
- 8,511.39
- Add GST on “X-A” (multiplying factor 0.2127)
- 72.60
- TOTAL
- 8,583.99
- Add 15% CPOH on “Y-A”
- 62.09
- TOTAL
- 8,646.08
- Add Cess @ 1% on “Z-A”
- 4.76
- Cost of 1 cum
- 8,650.84
- Say
- 8,650.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 211. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works