Providing and fixing in position Stainless steel Grade 304 plate-1.0 mm thick as per design for expansion joints

200 mm wide
Item number
5.43.1
Analysis basis
1 metre
Priced inputs
6
Derived rate
₹859.75/ METRE
D-01/RATE ANALYSISITEM 5.43.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.43.1 (Providing and fixing in position Stainless steel Grade 304 plate-1.0 mm thick as per design for expansion joints 200 mm wide) is derived from 6 priced inputs for 1 metre and works out to ₹859.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 5.43.1DETAIL OF COST FOR 1 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2393MAT1 mm thick Stainless Steel Cover plate grade 304kg1.6306.00489.60
8647MATStainless steal screws 30mm x4mm.Stainless steel screws 30 mm x4 mm100 nos0.0642.002.52
9977MATCarriage of materialL.S.1.32.272.95
0103LABBlacksmith 2nd classday0.067816.0054.67
0114LABBeldarday0.067736.0049.31
9999MATSundriesL.S.2.342.275.31
BUILD-UP TO RATE
TOTAL
604.36
Add 1 % Water charges on “W”
+6.04
TOTAL
610.40
Add GST on “X” (multiplying factor 0.2127)
+129.83
TOTAL
740.23
Add 15% CPOH on “Y”
+111.03
TOTAL
851.26
Add Cess @ 1% on “Z”
+8.51
Cost of 1 metre
859.77
SAY
₹859.75
D-02/SOURCEPRINTED PAGE 289
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
289

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 289. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.