Providing and fixing parallel threaded couplers conforming to IS code on “Reinforcement Couplers for Mechanical Splices of Bars for Concrete Reinforcement - Specification”, to reinforcement bars including threading, enlargement at connection by forging, protecting the prepared reinforcement bars and related operations as required to complete the works per direction of Engineerin-Charge
- Item number
- 5.42.5
- Analysis basis
- 1 Nos
- Priced inputs
- 3
- Derived rate
- ₹318.80/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.42.5 (Providing and fixing parallel threaded couplers conforming to IS code on “Reinforcement Couplers for Mechanical Splices of Bars for Concrete Reinforcement - Specification”, to reinforcement bars including threading, enlargement at connection by forging, protecting the prepared reinforcement bars and related operations as required to complete the works per direction of Engineerin-Charge Coupler for 32 mm diameter reinforcement bar) is derived from 3 priced inputs for 1 Nos and works out to ₹318.80 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2398 | MAT | Coupler 32 mm dia | each | 1 | 115.00 | 115.00 |
| 9999 | MAT | For placing in position and fixing | L.S. | 15.48 | 2.27 | 35.14 |
| 9999 | MAT | Tapard/Parallel threading charges | L.S. | 32.57 | 2.27 | 73.93 |
- TOTAL
- 224.07
- Add 1 % Water charges on “W”
- +2.24
- TOTAL
- 226.31
- Add GST on “X” (multiplying factor 0.2127)
- +48.14
- TOTAL
- 274.45
- Add 15% CPOH on “Y”
- +41.17
- TOTAL
- 315.62
- Add Cess @ 1% on “Z”
- +3.16
- Cost of 1 no
- 318.78
- SAY
- ₹318.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 289
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 289. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.