CPWD Analysis of Rates · Reinforced Cement Concrete
Providing and filling in position, blown bitumen in expansion joints
- Item number
- 5.26
- Analysis basis
- Details of cost for a joint of 300m length,
- Priced inputs
- 6
- Derived rate
- ₹74,854.65 / a joint
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.26 — Providing and filling in position, blown bitumen in expansion joints — is derived from 6 priced inputs for a joint and works out to ₹74,854.65 per a joint after water charges, GST, CPOH and cess. The full build-up is below.
- 2.5cm width and 15cm depth = 1.125 cum
- Cubical content of joint300x0.025x0.150=1.125 cum.
- Bitumen 85/25 @ 1050kg per cum.
- 1.125x1050kg = 1181.25kg
- = 1240.31 = 1.240 tonne
- For heating of bitumen @ 2.0 quintal per
- tonne of bitumen.
- 1.240x2.0=2.48q=0.248t
- Add wastage @ 5% = 59.06 kg.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0313 | Blown type petroleum bitumen of penetration 85/25 of approved qualityMaterial | tonne | 1.24 | 38,250.00 | 47,430.00 |
| 0370 | Coal (steam)Material | quintal | 2.48 | 500.00 | 1,240.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 2.52 | 897.00 | 2,260.44 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 2.52 | 816.00 | 2,056.32 |
| 0114 | BeldarLabour | day | 8.06 | 736.00 | 5,932.16 |
| 9999 | SundriesMaterial | L.S. | 121.16 | 2.27 | 275.03 |
- TOTAL
- 59,193.95
- Add 1 % Water charges on “W”
- 591.94
- TOTAL
- 59,785.89
- Add GST on “X” (multiplying factor 0.2127)
- 12,716.46
- TOTAL
- 72,502.35
- Add 15% CPOH on “Y”
- 10,875.35
- TOTAL
- 83,377.70
- Add Cess @ 1% on “Z”
- 833.78
- Cost for 1.125 cum
- 84,211.48
- cost for 1.00cum
- 74,854.65
- Say
- 74,854.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 268. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.