CPWD Analysis of Rates · Reinforced Cement Concrete

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level

Cold twisted bars

Item number
5.22.3
Analysis basis
Details of cost for 1 quintal-
Priced inputs
5
Derived rate
107.85 / Kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22.3 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Cold twisted bars — is derived from 5 priced inputs for 1 quintal and works out to ₹107.85 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Deformed twisted steel bars = 1.00 q
  • Wastage 5% = 0.05 q
  • Total = 1.05q
  • For straightening, cutting, bending, binding
  • and placing in position-
CodeInputUnitQuantityRate (INR)Amount (INR)
1005Twisted steel / deformed barsTwisted steel/ deformed TMT bars Fe-500DMaterialquintal1.055,550.005,827.50
9999Cover blockMaterialL.S.262.2759.02
0102Blacksmith 1st classLabourday1897.00897.00
0114BeldarLabourday1736.00736.00
9999Sundries and binding wireMaterialL.S.26.912.2761.09
TOTAL
7,580.61
Add 1 % Water charges on “W”
75.81
TOTAL
7,656.42
Add GST on “X” (multiplying factor 0.2127)
1,628.52
TOTAL
9,284.94
Add 15% CPOH on “Y”
1,392.74
TOTAL
10,677.68
Add Cess @ 1% on “Z”
106.78
Cost of one quintal
10,784.46
Cost of 1 Kg.
107.84
Say
107.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 259. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.