Skip to main content

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level

Hard drawn steel wire
Item number
5.22.2
Analysis basis
1 quintal
Priced inputs
4
Derived rate
₹95.80/ KG
D-01/RATE ANALYSISITEM 5.22.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.22.2 (Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Hard drawn steel wire) is derived from 4 priced inputs for 1 quintal and works out to ₹95.80 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Hard drawn steel wire = 1.00 q
  • Wastage 5% = 0.05 q
  • Total = 1.05 q
ANALYSIS OF RATES · ITEM 5.22.2DETAILS OF COST FOR 1 QUINTAL-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1224MATHard drawn steel wirequintal1.054,800.005,040.00
0102LABBlacksmith 1st classday1897.00897.00
0114LABBeldarday1736.00736.00
9999MATSundriesL.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
6,734.09
Add 1 % Water charges on “W”
+67.34
TOTAL
6,801.43
Add GST on “X” (multiplying factor 0.2127)
+1,446.66
TOTAL
8,248.09
Add 15% CPOH on “Y”
+1,237.21
TOTAL
9,485.30
Add Cess @ 1% on “Z”
+94.85
Cost of one quintal
9,580.15
Cost of 1 Kg.
95.80
SAY
₹95.80
D-02/SOURCEPRINTED PAGE 259
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
259

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 259. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREINFORCED CEMENT CONCRETE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.