Extra for providing and fixing expanded metal mesh of size 20x60 mm and strands 3.25 mm wide 1.6 mm thick weighing 3.64 kg per sqm for encasing of rolled steel sections in beams, columns and grillages, excluding cost of hangers
- Item number
- 5.21
- Priced inputs
- 5
- Derived rate
- ₹485.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 5.21 (Extra for providing and fixing expanded metal mesh of size 20x60 mm and strands 3.25 mm wide 1.6 mm thick weighing 3.64 kg per sqm for encasing of rolled steel sections in beams, columns and grillages, excluding cost of hangers) is derived from 5 priced inputs and works out to ₹485.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Deatail of cost for 10 sqm
- Expended metal 20 mm x 60 mm and 1.6
- mm thick = 10 sqm
- Wastage 5% = 0.5 sqm
- Total =10.50 sqm
- Cost of bending and placing in position
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1015 | MAT | Mild steel expanded metal 20x60 mm strandsMild steel expanded metal 20x60 mm strands 3.25 mm wide 1.60 mm thick | sqm | 10.5 | 280.00 | 2,940.00 |
| 9977 | MAT | Carriage of expended metal | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | MAT | Wire for tieing | L.S. | 13.52 | 2.27 | 30.69 |
| 0102 | LAB | Blacksmith 1st class | day | 0.25 | 897.00 | 224.25 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
- TOTAL
- 3,409.63
- Add 1 % Water charges on “W”
- +34.10
- TOTAL
- 3,443.73
- Add GST on “X” (multiplying factor 0.2127)
- +732.48
- TOTAL
- 4,176.21
- Add 15% CPOH on “Y”
- +626.43
- TOTAL
- 4,802.64
- Add Cess @ 1% on “Z”
- +48.03
- Cost of 10 sqm
- 4,850.67
- Cost of 1 sqm.
- 485.07
- SAY
- ₹485.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 258
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 258. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.