Providing and fixing factory made precast RCC perforated drain covers, having concrete of strength not less than M-25, of size 1000 x 450x50 mm, reinforced with 8 mm dia four nos longitudinal & 9 nos cross sectional T.M.T. hoop bars, including providing 50 mm dia perforations @ 100 to 125 mm c/c, including providing edge binding with M.S. flats of size 50 mm x 1.6 mm complete, all as per direction of Engineer-in-charge
- Item number
- 23.9
- Analysis basis
- 1 No
- Priced inputs
- 2
- Derived rate
- ₹1,399.95/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.9 (Providing and fixing factory made precast RCC perforated drain covers, having concrete of strength not less than M-25, of size 1000 x 450x50 mm, reinforced with 8 mm dia four nos longitudinal & 9 nos cross sectional T.M.T. hoop bars, including providing 50 mm dia perforations @ 100 to 125 mm c/c, including providing edge binding with M.S. flats of size 50 mm x 1.6 mm complete, all as per direction of Engineer-in-charge) is derived from 2 priced inputs for 1 No and works out to ₹1,399.95 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7762 | MAT | Precast R.C.C. perforated slab | each | 1 | 950.00 | 950.00 |
| 9988 | MAT | Carriage and fixing charges | L.S. | 15 | 2.27 | 34.05 |
- TOTAL
- 984.05
- Add 1 % Water charges on “W”
- +9.84
- TOTAL
- 993.89
- Add GST on “X” (multiplying factor 0.2127)
- +211.40
- TOTAL
- 1,205.29
- Add 15% CPOH on “Y”
- +180.79
- TOTAL
- 1,386.08
- Add Cess @ 1% on “Z”
- +13.86
- Cost of 1 No.
- 1,399.94
- SAY
- ₹1,399.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1878
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1878. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate