Providing and fixing factory made precast RCC perforated drain covers, having concrete of strength not less than M-25, of size 1000 x 450x50 mm, reinforced with 8 mm dia four nos longitudinal & 9 nos cross sectional T.M.T. hoop bars, including providing 50 mm dia perforations @ 100 to 125 mm c/c, including providing edge binding with M.S. flats of size 50 mm x 1.6 mm complete, all as per direction of Engineer-in-charge

Item number
23.9
Analysis basis
1 No
Priced inputs
2
Derived rate
₹1,399.95/ NO
D-01/RATE ANALYSISITEM 23.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.9 (Providing and fixing factory made precast RCC perforated drain covers, having concrete of strength not less than M-25, of size 1000 x 450x50 mm, reinforced with 8 mm dia four nos longitudinal & 9 nos cross sectional T.M.T. hoop bars, including providing 50 mm dia perforations @ 100 to 125 mm c/c, including providing edge binding with M.S. flats of size 50 mm x 1.6 mm complete, all as per direction of Engineer-in-charge) is derived from 2 priced inputs for 1 No and works out to ₹1,399.95 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 23.9DETAILS OF COST FOR 1 NO. RCC DRAIN COVER
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7762MATPrecast R.C.C. perforated slabeach1950.00950.00
9988MATCarriage and fixing chargesL.S.152.2734.05
BUILD-UP TO RATE
TOTAL
984.05
Add 1 % Water charges on “W”
+9.84
TOTAL
993.89
Add GST on “X” (multiplying factor 0.2127)
+211.40
TOTAL
1,205.29
Add 15% CPOH on “Y”
+180.79
TOTAL
1,386.08
Add Cess @ 1% on “Z”
+13.86
Cost of 1 No.
1,399.94
SAY
₹1,399.95
D-02/SOURCEPRINTED PAGE 1878
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1878

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1878. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSRAIN WATER HARVESTING & TUBE WELLS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.