Gravel packing in tubewell construction in accordance with IS: 4097, including providing gravel fine/ medium/ coarse, in required grading & sizes as per actual requirement, all complete as per direction of Engineer-in-charge
- Item number
- 23.8
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 3
- Derived rate
- ₹2,024.50 / Cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.8 — Gravel packing in tubewell construction in accordance with IS: 4097, including providing gravel fine/ medium/ coarse, in required grading & sizes as per actual requirement, all complete as per direction of Engineer-in-charge — is derived from 3 priced inputs for 1 cum and works out to ₹2,024.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- including carriage
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7772 | Pea GravelMaterial | cum | 1 | 1,200.00 | 1,200.00 |
| 0114 | BeldarLabour | day | 0.3 | 736.00 | 220.80 |
| 9999 | SundriesMaterial | L.S. | 1 | 2.27 | 2.27 |
- TOTAL
- 1,423.07
- Add 1 % Water charges on “W”
- 14.23
- TOTAL
- 1,437.30
- Add GST on “X” (multiplying factor 0.2127)
- 305.71
- TOTAL
- 1,743.01
- Add 15% CPOH on “Y”
- 261.45
- TOTAL
- 2,004.46
- Add Cess @ 1% on “Z”
- 20.04
- Cost of 1 Cum.
- 2,024.50
- Say
- 2,024.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1878. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.