Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing (CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineer -in-charge

200 mm nominal size dia
Item number
23.3.3
Analysis basis
100 metres
Priced inputs
4
Derived rate
₹1,113.35/ METRE
D-01/RATE ANALYSISITEM 23.3.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.3.3 (Supplying, assembling, lowering and fixing in vertical position in bore well, unplasticized PVC medium well casing (CM) pipe of required dia, conforming to IS: 12818, including required hire and labour charges, fittings & accessories etc. all complete, for all depths, as per direction of Engineer -in-charge 200 mm nominal size dia) is derived from 4 priced inputs for 100 metres and works out to ₹1,113.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 23.3.3DETAILS OF COST FOR 100 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7746MATuPVC blind pipe 200 mm dia as per IS: 12818PVC blind pipe 200 mm dia as per IS: 12818metre100775.0077,500.00
0114LABBeldarday0.5736.00368.00
0115LABCoolieday0.5736.00368.00
9999MATSundriesL.S.10.072.2722.86
BUILD-UP TO RATE
TOTAL
78,258.86
Add 1 % Water charges on “W”
+782.59
TOTAL
79,041.45
Add GST on “X” (multiplying factor 0.2127)
+16,812.12
TOTAL
95,853.57
Add 15% CPOH on “Y”
+14,378.04
TOTAL
1,10,231.61
Add Cess @ 1% on “Z”
+1,102.32
Cost of 100 metres
1,11,333.93
Cost of 1 metre
1,113.34
SAY
₹1,113.35
D-02/SOURCEPRINTED PAGE 1875
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1875

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1875. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.