Providing and fixing M.S. clamp of required dia to the top of casing/ housing pipe of tubewell as per IS: 2800 (part I), including necessary bolts & nuts of required size complete

200 mm clamp
Item number
23.14.3
Analysis basis
1 No
Priced inputs
2
Derived rate
₹2,293.65/ NO
D-01/RATE ANALYSISITEM 23.14.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 23.14.3 (Providing and fixing M.S. clamp of required dia to the top of casing/ housing pipe of tubewell as per IS: 2800 (part I), including necessary bolts & nuts of required size complete 200 mm clamp) is derived from 2 priced inputs for 1 No and works out to ₹2,293.65 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Clamps made of MS flat of size 100x10mm
  • thick1x2.40 mt.x7.80 kg per mt.=18.72 kg.
ANALYSIS OF RATES · ITEM 23.14.3DETAILS OF COST FOR 1 NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.10.1 of SH:Steel WorkRate as per item 10.1kg18.72117.352,196.79
9999MATSundries, nuts and bolts etc.L.S.302.2768.10
BUILD-UP TO RATE
TOTAL
2,264.89
Add 1 % Water charges on “W-A”
+0.68
TOTAL
2,265.57
Add GST on “X-A” (multiplying factor 0.2127)
+14.63
TOTAL
2,280.20
Add 15% CPOH on “Y-A”
+12.51
TOTAL
2,292.71
Add Cess @ 1% on “Z-A”
+0.96
Cost of 1 No
2,293.67
SAY
₹2,293.65
D-02/SOURCEPRINTED PAGE 1884
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1884

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1884. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSRAIN WATER HARVESTING & TUBE WELLS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.