CPWD Analysis of Rates · Pile Work
Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge Group of two or more piles upto 50 tonne Safe capacity
Routine test (Test Load 1.5 times the Safe capacity)
- Item number
- 20.6.3.2
- Analysis basis
- Details of cost for 1 test
- Priced inputs
- 1
- Derived rate
- ₹40,545.15 / test
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.6.3.2 — Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge Group of two or more piles upto 50 tonne Safe capacity Routine test (Test Load 1.5 times the Safe capacity) — is derived from 1 priced inputs for 1 test and works out to ₹40,545.15 per test after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7251 | Cyclic verticle load testing of piles in accordance with IS : 2911 (Part-IV) including prepration of pile head etc. for Group of two piles upto 50 tonne capacity eachCyclic vertical load testing of piles in accordance with IS : 2911 (Part- IV) including preparation of pile head etc. for Group of two piles up to 50 tonne capacity eachMaterial | per test | 1 | 28,500.00 | 28,500.00 |
- TOTAL
- 28,500.00
- Add 1 % Water charges on “W”
- 285.00
- TOTAL
- 28,785.00
- Add GST on “X” (multiplying factor 0.2127)
- 6,122.57
- TOTAL
- 34,907.57
- Add 15% CPOH on “Y”
- 5,236.14
- TOTAL
- 40,143.71
- Add Cess @ 1% on “Z”
- 401.44
- Cost per test
- 40,545.15
- Say
- 40,545.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1808. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works