Providing, driving (with vibrating pile driving hammer complete with power units & accessories) and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length below the pile cap in M-25 cement concrete to carry safe working load not less than specified with a central through preformed hole with M.S. black pipe of dia, 40 mm for grouting with cement sand grouting of mix 1:2 (1cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)
- Item number
- 20.5.2
- Analysis basis
- 20 m
- Priced inputs
- 11
- Derived rate
- ₹4,766.25/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.5.2 (Providing, driving (with vibrating pile driving hammer complete with power units & accessories) and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length below the pile cap in M-25 cement concrete to carry safe working load not less than specified with a central through preformed hole with M.S. black pipe of dia, 40 mm for grouting with cement sand grouting of mix 1:2 (1cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap) 450 mm dia piles) is derived from 11 priced inputs for 20 m and works out to ₹4,766.25 per m after water charges, GST, CPOH and cess. The full build-up is below.
- Concrete -3.14/4x(0.45)²x20 = 3.18 cu
- Cement mortar 1:2 for grout
- Work supervisor
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1 | cum | 3.18 | 9,504.75 | 30,225.11 | |
| SUB | Add Rate as per item no 5.19 of SH : RCCRate as per item 5.19 | cum | 3.18 | 16,089.40 | 51,164.29 | |
| SUB | Deduct Rate as per item no 5.1.3 SH : RCCRate as per item 5.1.3 | cum | -3.18 | 8,583.40 | -27,295.21 | |
| SUB | Rate as per Item Number 3.7 of SH: MortarsRate as per item 3.7 | cum | 0.025 | 5,584.50 | 139.61 | |
| 9999 | MAT | Sundries | L.S. | 442 | 2.27 | 1,003.34 |
| 7181 | MAT | C.I. pile shoe of 80 kg per pileC.I. pile shoe | kilogram | 80 | 52.00 | 4,160.00 |
| 7182 | MAT | M.S. clamps for pile shoe of 35 kg per pileM.S. clamps for pile shoe of 35 kg per pile | kilogram | 35 | 45.00 | 1,575.00 |
| 0027 | MACH | Hire and running charges of vibrating pile driving hammer complete with power unit and accessories | day | 0.38 | 33,500.00 | 12,730.00 |
| 0028 | MACH | Hire and running charges of crane 20 tonne capacity | day | 0.06 | 7,850.00 | 471.00 |
| 0130 | LAB | Mistry | day | 1.08 | 897.00 | 968.76 |
| 0114 | LAB | Beldar | day | 10.78 | 736.00 | 7,934.08 |
- Total
- 83,075.98
- Add 1% water charges on “W -A”
- +289.82
- TOTAL
- 83,365.80
- Add GST on “X-A” (multiplying factor 0.2127)
- +6,226.07
- TOTAL
- 89,591.87
- Add 15% CP & OH on “Y-A”
- +5,324.65
- TOTAL
- 94,916.52
- Add 1% cess on “Z -A”
- +408.22
- Cost of 20 m pile
- 95,324.74
- Cost for 1 m pile
- 4,766.24
- SAY
- ₹4,766.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1803
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1803. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.