Providing, driving (with vibrating pile driving hammer complete with power units & accessories) and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length below the pile cap in M-25 cement concrete to carry safe working load not less than specified with a central through preformed hole with M.S. black pipe of dia, 40 mm for grouting with cement sand grouting of mix 1:2 (1cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap)

400 mm dia piles
Item number
20.5.1
Analysis basis
20 m
Priced inputs
11
Derived rate
₹3,727.80/ M
D-01/RATE ANALYSISITEM 20.5.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.5.1 (Providing, driving (with vibrating pile driving hammer complete with power units & accessories) and installing driven Pre-cast reinforced cement concrete piles of specified diameter and length below the pile cap in M-25 cement concrete to carry safe working load not less than specified with a central through preformed hole with M.S. black pipe of dia, 40 mm for grouting with cement sand grouting of mix 1:2 (1cement : 2 coarse sand) under sufficient positive pressure to ensure complete filling including centring, shuttering, driving and removing the steel casing pipe and lifting casing etc. complete but excluding the cost of steel reinforcement. (Length of pile for payment shall be measured from top of the shoe to the bottom of pile cap) 400 mm dia piles) is derived from 11 priced inputs for 20 m and works out to ₹3,727.80 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Concrete -3.14/4x(0.40)²x20 = 2.51 cum
  • Cement mortar 1:2 for grout
  • Work supervisor
ANALYSIS OF RATES · ITEM 20.5.1DETAILS OF COST FOR 20 M LENGTH OF PILE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1cum2.519,504.7523,856.92
SUBAdd Rate as per item no 5.19 of SH : RCCRate as per item 5.19cum2.5116,089.4040,384.39
SUBDeduct Rate as per item no 5.1.3 SH : RCCRate as per item 5.1.3cum-2.518,583.40-21,544.33
SUBRate as per Item Number 3.7 of SH: MortarsRate as per item 3.7cum0.0255,584.50139.61
9999MATSundriesL.S.4422.271,003.34
7181MATC.I. pile shoe of 80 kg per pileC.I. pile shoekilogram8052.004,160.00
7182MATM.S. clamps for pile shoe of 35 kg per pileM.S. clamps for pile shoe of 35 kg per pilekilogram3545.001,575.00
0027MACHHire and running charges of vibrating pile driving hammer complete with power unit and accessoriesday0.3833,500.0012,730.00
0028MACHHire and running charges of crane 20 tonne capacityday0.067,850.00471.00
0130LABMistryday0.12897.00107.64
0114LABBeldarday3736.002,208.00
BUILD-UP TO RATE
Total
65,091.57
Add 1% water charges on “W -A”
+223.95
TOTAL
65,315.52
Add GST on “X-A” (multiplying factor 0.2127)
+4,810.96
TOTAL
70,126.48
Add 15% CP & OH on “Y-A”
+4,114.43
TOTAL
74,240.91
Add 1% cess on “Z -A”
+315.44
Cost of 20 m pile
74,556.35
Cost for 1 m pile
3,727.82
SAY
₹3,727.80
D-02/SOURCEPRINTED PAGE 1802
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1802

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1802. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSPILE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.