Skip to main content

CPWD Analysis of Rates · Pile Work

Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)

1200 mm dia piles

Item number
20.1.7
Analysis basis
Details of cost for 9 m length of pile
Priced inputs
8
Derived rate
16,671.05 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.1.7 Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) : 1200 mm dia piles — is derived from 8 priced inputs for 9 m and works out to ₹16,671.05 per m after water charges, GST, CPOH and cess. The full build-up is below.

  • Concrete 3.14/4x1.2²x9 = 10.17 cum
  • Work supervisor
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1Sub-analysiscum10.179,504.7596,663.31
9999SundriesMaterialL.S.7102.271,611.70
7181C.I. pile shoe of 80 kg per pile @ 80 kg per pileC.I. pile shoeMaterialkilogram8052.004,160.00
7182M.S. clamps for pile shoe of 35 kg per pileM.S. clamps for pile shoe of 35 kg per pileMaterialkilogram3545.001,575.00
0024Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteMachineryday0.6739,500.0026,465.00
0025Hire and running charges of light crane.Hire and running charges of light craneMachineryday0.063,900.00234.00
0130MistryLabourday0.18897.00161.46
0114BeldarLabourday4.5736.003,312.00
Total
1,34,182.47
Add 1% water charges on “W -A”
375.19
TOTAL
1,34,557.66
Add GST on “X-A” (multiplying factor 0.2127)
8,060.13
TOTAL
1,42,617.79
Add 15% CP & OH on “Y-A”
6,893.17
TOTAL
1,49,510.96
Add 1% cess on “Z -A”
528.48
Cost of 9 m pile
1,50,039.44
Cost for 1 m pile
16,671.05
Say
16,671.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1788. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works