CPWD Analysis of Rates · Pile Work
Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)
1200 mm dia piles
- Item number
- 20.1.7
- Analysis basis
- Details of cost for 9 m length of pile
- Priced inputs
- 8
- Derived rate
- ₹16,671.05 / m
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.1.7 — Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) : 1200 mm dia piles — is derived from 8 priced inputs for 9 m and works out to ₹16,671.05 per m after water charges, GST, CPOH and cess. The full build-up is below.
- Concrete 3.14/4x1.2²x9 = 10.17 cum
- Work supervisor
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1Sub-analysis | cum | 10.17 | 9,504.75 | 96,663.31 | |
| 9999 | SundriesMaterial | L.S. | 710 | 2.27 | 1,611.70 |
| 7181 | C.I. pile shoe of 80 kg per pile @ 80 kg per pileC.I. pile shoeMaterial | kilogram | 80 | 52.00 | 4,160.00 |
| 7182 | M.S. clamps for pile shoe of 35 kg per pileM.S. clamps for pile shoe of 35 kg per pileMaterial | kilogram | 35 | 45.00 | 1,575.00 |
| 0024 | Hire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteMachinery | day | 0.67 | 39,500.00 | 26,465.00 |
| 0025 | Hire and running charges of light crane.Hire and running charges of light craneMachinery | day | 0.06 | 3,900.00 | 234.00 |
| 0130 | MistryLabour | day | 0.18 | 897.00 | 161.46 |
| 0114 | BeldarLabour | day | 4.5 | 736.00 | 3,312.00 |
- Total
- 1,34,182.47
- Add 1% water charges on “W -A”
- 375.19
- TOTAL
- 1,34,557.66
- Add GST on “X-A” (multiplying factor 0.2127)
- 8,060.13
- TOTAL
- 1,42,617.79
- Add 15% CP & OH on “Y-A”
- 6,893.17
- TOTAL
- 1,49,510.96
- Add 1% cess on “Z -A”
- 528.48
- Cost of 9 m pile
- 1,50,039.44
- Cost for 1 m pile
- 16,671.05
- Say
- 16,671.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1788. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.