Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap)

1000 mm dia piles
Item number
20.1.6
Analysis basis
10 m
Priced inputs
8
Derived rate
₹12,748.45/ M
D-01/RATE ANALYSISITEM 20.1.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 20.1.6 (Providing, driving with hydraulic piling rigs with power units and installing driven cast-insitu reinforced cement concrete piles of grade M-25 of specified diameter and length below the pile cap, to carry safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of shoe and the length of pile to be embedded in the pile cap etc. all complete. (Length of pile for payment shall be measured from top of shoe to the bottom of pile cap) : 1000 mm dia piles) is derived from 8 priced inputs for 10 m and works out to ₹12,748.45 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Concrete 3.14/4x1.00²x10 = 7.85 cum
  • Work supervisor
ANALYSIS OF RATES · ITEM 20.1.6DETAILS OF COST FOR 10 M LENGTH OF PILE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no 5.33.1.1 of SH : RCC WorkRate as per item 5.33.1.1cum7.859,504.7574,612.29
9999MATSundriesL.S.5502.271,248.50
7181MATC.I. pile shoe of 80 kg per pile @ 80 kg per pileC.I. pile shoekilogram8052.004,160.00
7182MATM.S. clamps for pile shoe of 35 kg per pileM.S. clamps for pile shoe of 35 kg per pilekilogram3545.001,575.00
0024MACHHire and running charges of hydraulic piling rig with power unit etc. including complete accessories and shifting at siteday0.6839,500.0026,860.00
0025MACHHire and running charges of light crane.Hire and running charges of light craneday0.063,900.00234.00
0130LABMistryday0.16897.00143.52
0114LABBeldarday4736.002,944.00
BUILD-UP TO RATE
Total
1,11,777.31
Add 1% water charges on “W -A”
+371.65
TOTAL
1,12,148.96
Add GST on “X-A” (multiplying factor 0.2127)
+7,984.05
TOTAL
1,20,133.01
Add 15% CP & OH on “Y-A”
+6,828.11
TOTAL
1,26,961.12
Add 1% cess on “Z -A”
+523.49
Cost of 10 m pile
1,27,484.61
Cost for 1 m pile
12,748.46
SAY
₹12,748.45
D-02/SOURCEPRINTED PAGE 1788
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1788

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1788. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSPILE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.