Providing and fixing factory made solid Foam uPVC profile for kitchen cabinet frame (45 x 20 mm) of approved shade, quality and make. The profile shall be laminated on both sides, made from rigid foam sheets (Single extruded) having density 600 Kg/cum and the exposed edges sealed with PVC edge beading of same shade and colour. The frame shall be fire retardent with necessary screw holding capacity. Frame shall be fixed to wall using Expendable Fastner with necesary stainless steel screws, all complete as per direction of Engineer-in-charge

Item number
26.9
Analysis basis
kitchen cabinate
Priced inputs
6
Derived rate
₹450.95/ KITCHEN CABINATE
D-01/RATE ANALYSISITEM 26.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.9 (Providing and fixing factory made solid Foam uPVC profile for kitchen cabinet frame (45 x 20 mm) of approved shade, quality and make. The profile shall be laminated on both sides, made from rigid foam sheets (Single extruded) having density 600 Kg/cum and the exposed edges sealed with PVC edge beading of same shade and colour. The frame shall be fire retardent with necessary screw holding capacity. Frame shall be fixed to wall using Expendable Fastner with necesary stainless steel screws, all complete as per direction of Engineer-in-charge) is derived from 6 priced inputs for kitchen cabinate and works out to ₹450.95 per kitchen cabinate after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (2.00 x 0.45)+(2.00+0.615)= 2.13 mtr
ANALYSIS OF RATES · ITEM 26.9DETAILS OF COST FOR KITCHEN CABINATE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2491MATPre laminated both side solid foam uPVC profile (45x20mm)Pre laminated both side solid foam uPVC profile (45x20 mm)metre2.13136.00289.68
2493MATPVC edge beadingmetre4.2633.00140.58
2494MATExpandable fastner with plastic sleeveeach87.0056.00
8210MATStainless steel screws 50 mm100 Nos0.08320.0025.60
0111LABCarpenter 1st classday0.1897.0089.70
0114LABBeldarday0.1736.0073.60
BUILD-UP TO RATE
TOTAL
675.16
Add 1 % Water charges on “W”
+6.75
TOTAL
681.91
Add GST on “X” (multiplying factor 0.2127)
+145.04
TOTAL
826.95
Add 15% CPOH on “Y”
+124.04
TOTAL
950.99
Add Cess @ 1% on “Z”
+9.51
Cost for 2.13 metre
960.50
Cost for 1 metre
450.94
SAY
₹450.95
D-02/SOURCEPRINTED PAGE 1919
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1919

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1919. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.