CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/ window/Clerestory windows & other Frames/Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/ rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 gms) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 750 kg/cum, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2, modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (M.S hold fast/lugs or SS dash fasteners shall be paid for separately). Note: For WPC solid door/window frames, minus 5mm tolerance in dimensions i.e depth and width of profile shall be acceptable. Variation in profile dimensions on plus side shall be acceptable but no extra payment on this account shall be made

Frame size 45 x 70 mm

Item number
26.86.1
Analysis basis
Details of cost of door frame/ chowkhat of
Priced inputs
5
Derived rate
705.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.86.1 Providing and fixing factory made single extruded WPC (Wood Polymer Composite) solid door/ window/Clerestory windows & other Frames/Chowkhat comprising of virgin PVC polymer of K value 58-60 (Suspension Grade), calcium carbonate and natural fibers (wood powder/ rice husk/ wheat husk) and non toxic additives (maximum toxicity index of 12 for 100 gms) fabricated with miter joints after applying PVC solvent cement and screwed with full body threaded star headed SS screws having minimum frame density of 750 kg/cum, screw withdrawal strength of 2200 N (Face) & 1100 N (Edge), minimum compressive strength of 58 N/mm2, modulus of elasticity 900 N/mm2 and resistance to spread of flame of Class A category with property of being termite/borer proof, water/moisture proof and fire retardant and fixed in position with M.S hold fast/lugs/SS dash fasteners of required dia and length complete as per direction of Engineer-InCharge. (M.S hold fast/lugs or SS dash fasteners shall be paid for separately). Note: For WPC solid door/window frames, minus 5mm tolerance in dimensions i.e depth and width of profile shall be acceptable. Variation in profile dimensions on plus side shall be acceptable but no extra payment on this account shall be made Frame size 45 x 70 mm — is derived from 5 priced inputs and works out to ₹705.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • size 1.00x2.10m (1.00+2.1+2.10=5.20m)
CodeInputUnitQuantityRate (INR)Amount (INR)
5747Factory made single extruded WPC (Wood Polymer Composite) solid wood/ window/ clerestory window frames/ chowkhat i/c carriage of frame Frame size 45x 70mmFactory made single extruded WPC (Wood Polymer Composite) solid door/window, clerestory windows & other Frames/Chowkhat of frame size 45 x 70 mmMaterialmetre5.2385.002,002.00
0156Carpenter (average)Labourday0.1857.0085.70
0155Mason (average)Labourday0.17857.00145.69
0114BeldarLabourday0.44736.00323.84
9999Sundries includes PVC solvent cement and SS screwsMaterialL.S.102.2722.70
TOTAL
2,579.93
Add 1 % Water charges on “W”
25.80
TOTAL
2,605.73
Add GST on “X” (multiplying factor 0.2127)
554.24
TOTAL
3,159.97
Add 15% CPOH on “Y”
474.00
TOTAL
3,633.97
Add Cess @ 1% on “Z”
36.34
Cost of 5.20 metre
3,670.31
Cost of 1 metre
705.83
Say
705.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2032. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.