Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tiestrips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge

Bi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse direction
Item number
26.85.3
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹416.35/ SQM
D-01/RATE ANALYSISITEM 26.85.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.85.3 (Supplying and laying of Bi-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement of granular road base and sub base, area stalilization, track bed stabilization, load transfer platforms Including accessories like tiestrips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required etc. complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Bi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse direction) is derived from 4 priced inputs for 300 Sqm and works out to ₹416.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIALS:
  • ments geogrid for wastage and accessories
  • like tie-strips, nuts and bolts and loops/lungs
  • for joining reinforcing elements with the
  • facia panels, overlaps and other protective
  • elements for geogrid and all other activities
  • required to complete the item in all respect
  • LABOUR:
  • Add 5 percent of the cost of reinforcing ele-
ANALYSIS OF RATES · ITEM 26.85.3DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8990MATBi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse directionBi Axial Woven polyster geogrid of minimum tensile strength 60KN/m in both Longitudinal and Transverse direction.sqm300256.0076,800.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
including transportation.i.e 5% of (P)
+3,840.00
Total
87,797.76
Add 1 % Water charges on “W”
+877.98
TOTAL
88,675.74
Add GST on “X” (multiplying factor 0.2127)
+18,861.33
TOTAL
1,07,537.07
Add 15% CPOH on “Y”
+16,130.56
TOTAL
1,23,667.63
Add Cess @ 1% on “Z”
+1,236.68
Cost of 300 sqm
1,24,904.31
Cost of 1 sqm
416.35
SAY
₹416.35
D-02/SOURCEPRINTED PAGE 2031
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2031

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2031. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.