Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge

Uni Axial Woven polyster geogrid of minimum tensile strength 150KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction
Item number
26.84.6
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹580.65/ SQM
D-01/RATE ANALYSISITEM 26.84.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.84.6 (Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Uni Axial Woven polyster geogrid of minimum tensile strength 150KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction) is derived from 4 priced inputs for 300 Sqm and works out to ₹580.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIALS:
  • ments geogrid for wastage and accessories
  • like tie-strips, nuts and bolts and loops/lungs
  • for joining reinforcing elements with the
  • facia panels, overlaps and other protective
  • elements for geogrid and all other activities
  • required to complete the item in all respect
  • LABOUR:
  • Add 5 percent of the cost of reinforcing ele-
ANALYSIS OF RATES · ITEM 26.84.6DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8984MATUni Axial Woven polyster geogrid of minimum tensile strength 150KN/m in the Longitudinal direction and 30 KN/m in the Transverse directionUni Axial Woven polyster geogrid of minimum tensile strength 150KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction.sqm300366.001,09,800.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
including transportation. i.e 5% of (P)
+5,490.00
Total
1,22,447.76
Add 1 % Water charges on “W”
+1,224.48
TOTAL
1,23,672.24
Add GST on “X” (multiplying factor 0.2127)
+26,305.09
TOTAL
1,49,977.33
Add 15% CPOH on “Y”
+22,496.60
TOTAL
1,72,473.93
Add Cess @ 1% on “Z”
+1,724.74
Cost of 300 sqm
1,74,198.67
Cost of 1 sqm
580.66
SAY
₹580.65
D-02/SOURCEPRINTED PAGE 2027
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2027

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2027. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.