Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge
- Item number
- 26.84.5
- Analysis basis
- 300 Sqm
- Priced inputs
- 4
- Derived rate
- ₹470.10/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.84.5 (Supplying and laying of Uni-Axial Woven Polyster Geogrid conforming to MORTH 3100 and IRC113, as soil reinforcement/basal reinforcement including accessories like tie-strips, nuts & bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps and other protective elements for synthetic geo-grids and all other activities required for reinforced soil walls, slopes etc complete as per design requirements, manufacturer specifications and as per direction of engineer-incharge Uni Axial Woven polyster geogrid of minimum tensile strength 120KN/m in the Longitudinal direction and 30 KN/m in the Transverse direction) is derived from 4 priced inputs for 300 Sqm and works out to ₹470.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIALS:
- ments geogrid for wastage and accessories
- like tie-strips, nuts and bolts and loops/lungs
- for joining reinforcing elements with the
- facia panels, overlaps and other protective
- elements for geogrid and all other activities
- required to complete the item in all respect
- LABOUR:
- Add 5 percent of the cost of reinforcing ele-
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8983 | MAT | Uni Axial Woven polyster geogrid of minimum tensile strength 120KN/m in the Longitudinal direction and 30KN/m in the Transverse directionUni Axial Woven polyster geogrid of minimum tensile strength 120KN/m in the Longitudinal direction and 30KN/m in the Transverse direction. | sqm | 300 | 292.00 | 87,600.00 |
| 0128 | LAB | Mate | day | 0.36 | 816.00 | 293.76 |
| 0114 | LAB | Beldar | day | 6 | 736.00 | 4,416.00 |
| 0139 | LAB | Skilled BeldarSkilled Beldar (for floor rubbing etc.) | day | 3 | 816.00 | 2,448.00 |
- including transportation.i.e 5% of (P)
- +4,380.00
- Total
- 99,137.76
- Add 1 % Water charges on “W”
- +991.38
- TOTAL
- 1,00,129.14
- Add GST on “X” (multiplying factor 0.2127)
- +21,297.47
- TOTAL
- 1,21,426.61
- Add 15% CPOH on “Y”
- +18,213.99
- TOTAL
- 1,39,640.60
- Add Cess @ 1% on “Z”
- +1,396.41
- Cost of 300 sqm
- 1,41,037.01
- Cost of 1 sqm
- 470.12
- SAY
- ₹470.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 2027
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2027. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.