Providing & Laying of levelling sim pads required sizes (5x5cm to 10x10cm) of PVC / Rubber to adjust level of bearing surface of supporting members as per the direction of Engineer in charge

10 mm thick
Item number
26.79.3
Analysis basis
100 Nos
Priced inputs
4
Derived rate
₹51.65/ NOS
D-01/RATE ANALYSISITEM 26.79.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.79.3 (Providing & Laying of levelling sim pads required sizes (5x5cm to 10x10cm) of PVC / Rubber to adjust level of bearing surface of supporting members as per the direction of Engineer in charge 10 mm thick) is derived from 4 priced inputs for 100 Nos and works out to ₹51.65 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 26.79.3DETAIL OF COST FOR 100 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0248MAT10 mm thick sim padeach10027.002,700.00
9977MATCarriage of materialL.S52.2711.35
0116LABFitter (Grade-1)Fitter (grade 1)day1897.00897.00
9999MATSundriesLS102.2722.70
BUILD-UP TO RATE
TOTAL
3,631.05
Add 1 % Water charges on “W”
+36.31
TOTAL
3,667.36
Add GST on “X” (multiplying factor 0.2127)
+780.05
TOTAL
4,447.41
Add 15% CPOH on “Y”
+667.11
TOTAL
5,114.52
Add Cess @ 1% on “Z”
+51.15
Cost for100 Nos
5,165.67
Cost of each
51.66
SAY
₹51.65
D-02/SOURCEPRINTED PAGE 2020
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
2020

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 2020. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.