Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge

Item number
26.72
Analysis basis
Details of cost for 10 sqm
Priced inputs
7
Derived rate
829.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.72 Providing and laying 60mm thick factory made cement concrete paver block of approved shape and colour of M -30 grade made of C&D waste by block making machine with vibratory compaction laid in required pattern and including over 50mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge — is derived from 7 priced inputs for 10 sqm and works out to ₹829.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • Bedding layer - 50mm thick
  • 10x0.050=0.50 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
7776Concrete paver block of grade M-30 made of C&D waste (60mm thickness)Concrete paver block of grade M-30 made of C&D waste (60 mm thickness)Materialsqm10300.003,000.00
0982Coarse sand (zone III)Materialcum0.51,450.00725.00
0983Fine sand (zone IV)Materialcum0.15980.00147.00
0123Mason (brick layer) 1st classMason 1st classLabourday0.5897.00448.50
0124Mason 2nd classMason 2nd classLabourday0.5816.00408.00
0114BeldarLabourday1736.00736.00
0115CoolieLabourday0.5736.00368.00
Total
5,832.50
Add 1 % Water charges on “W”
58.33
TOTAL
5,890.83
Add GST on “X” (multiplying factor 0.2127)
1,252.98
TOTAL
7,143.81
Add 15% CPOH on “Y”
1,071.57
TOTAL
8,215.38
Add Cess @ 1% on “Z”
82.15
Cost of 10 sqm
8,297.53
Cost of 1 sqm
829.75
Say
829.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1999. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.