Providing and laying half block masonry with factory made Precast concrete solid blocks of 100 mm thickness of grade M10 made of C&D waste from approved manufacturer in superstructure above plinth level up to floor V level

Cement mortar 1:4 (1 cement : 4 coarse sand)

Item number
26.71.1
Analysis basis
Details of cost for 100 sqm
Priced inputs
8
Derived rate
1,099.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.71.1 Providing and laying half block masonry with factory made Precast concrete solid blocks of 100 mm thickness of grade M10 made of C&D waste from approved manufacturer in superstructure above plinth level up to floor V level: Cement mortar 1:4 (1 cement : 4 coarse sand) — is derived from 8 priced inputs for 100 sqm and works out to ₹1,099.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • MATERIAL:
  • Cement mortar 1 : 4 (1 cement : 4 coarse sand)
  • Extra labour for lifting of materials
  • (above floor two level upto floor five
  • level=1.13x0.10x100=11.30)
CodeInputUnitQuantityRate (INR)Amount (INR)
8658Precast C&D waste concrete blockMaterial1000 Nos1.16130,100.0034,946.10
Rate as per item No 3.9 of SH: MortarRate as per item 3.9Sub-analysiscum0.7084,211.702,981.88
9999SundriesMaterialL.S.135.22.27306.90
0123Mason (brick layer) 1st classMason 1st classLabourday6897.005,382.00
0124Mason 2nd classMason 2nd classLabourday6816.004,896.00
0115CoolieLabourday20736.0014,720.00
0101BhistiLabourday7816.005,712.00
0115CoolieLabourday11.3736.008,316.80
Total
77,261.68
Add 1 % Water charges on “W”
772.62
TOTAL
78,034.30
Add GST on “X” (multiplying factor 0.2127)
16,597.90
TOTAL
94,632.20
Add 15% CPOH on “Y”
14,194.83
TOTAL
1,08,827.03
Add Cess @ 1% on “Z”
1,088.27
Cost of 100 sqm
1,09,915.30
Cost of 1 sqm
1,099.15
Say
1,099.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1999. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.