Skip to main content

Providing and laying factory made Precast concrete solid blocks of 200 mm thickness of grade M10 made of C&D waste from approved manufacturer in superstructure above plinth level up to floor V level

Cement mortar 1:6 (1 cement : 6 coarse sand)
Item number
26.69.1
Analysis basis
10 cum
Priced inputs
9
Derived rate
₹9,844.65/ CUM
D-01/RATE ANALYSISITEM 26.69.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.69.1 (Providing and laying factory made Precast concrete solid blocks of 200 mm thickness of grade M10 made of C&D waste from approved manufacturer in superstructure above plinth level up to floor V level Cement mortar 1:6 (1 cement : 6 coarse sand)) is derived from 9 priced inputs for 10 cum and works out to ₹9,844.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • Cement mortar 1 : 6 (1 cement : 6 coarse sand)
  • Extra labour element required for lifting of
  • materials (above floor two level upto floor
  • five level)
ANALYSIS OF RATES · ITEM 26.69.1DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8658MATPrecast C&D waste concrete block1000 Nos1.10930,100.0033,380.90
SUBRate as per item No 3.11 of SH: MortarRate as per item 3.11cum1.133,541.404,001.78
9999MATSundriesL.S.27.32.2761.97
0123LABMason (brick layer) 1st classMason 1st classday4.7897.004,215.90
0124LABMason 2nd classMason 2nd classday4.7816.003,835.20
0115LABCoolieday18736.0013,248.00
0101LABBhistiday2816.001,632.00
9999MATScaffoldingL.S.223.62.27507.57
0115LABCoolieday11.3736.008,316.80
BUILD-UP TO RATE
Total
69,200.12
Add 1 % Water charges on “W”
+692.00
TOTAL
69,892.12
Add GST on “X” (multiplying factor 0.2127)
+14,866.05
TOTAL
84,758.17
Add 15% CPOH on “Y”
+12,713.73
TOTAL
97,471.90
Add Cess @ 1% on “Z”
+974.72
Cost of 10 cum
98,446.62
Cost of 1 cum
9,844.66
SAY
₹9,844.65
D-02/SOURCEPRINTED PAGE 1998
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1998

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1998. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.