Providing and laying factory made Precast concrete solid blocks of 200 mm thickness of grade M10 made of C&D waste from approved manufacturer in foundation and plinth in

Cement mortar 1:6 (1 cement : 6 coarse sand)
Item number
26.68.1
Analysis basis
10 cum
Priced inputs
7
Derived rate
₹7,387.25/ CUM
D-01/RATE ANALYSISITEM 26.68.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.68.1 (Providing and laying factory made Precast concrete solid blocks of 200 mm thickness of grade M10 made of C&D waste from approved manufacturer in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand)) is derived from 7 priced inputs for 10 cum and works out to ₹7,387.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • MATERIAL:
  • Cement mortar 1 : 6 (1 cement : 6 coarse
  • sand)
ANALYSIS OF RATES · ITEM 26.68.1DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8658MATPrecast C&D waste concrete block1000 Nos1.10930,100.0033,380.90
SUBRate as per item No 3.11 of SH: MortarRate as per item 3.11cum1.133,541.404,001.78
9999MATSundriesL.S.27.32.2761.97
0123LABMason (brick layer) 1st classMason 1st classday3.3897.002,960.10
0124LABMason 2nd classMason 2nd classday3.3816.002,692.80
0115LABCoolieday10736.007,360.00
0101LABBhistiday1.8816.001,468.80
BUILD-UP TO RATE
Total
51,926.35
Add 1 % Water charges on “W”
+519.26
TOTAL
52,445.61
Add GST on “X” (multiplying factor 0.2127)
+11,155.18
TOTAL
63,600.79
Add 15% CPOH on “Y”
+9,540.12
TOTAL
73,140.91
Add Cess @ 1% on “Z”
+731.41
Cost of 10 cum
73,872.32
Cost of 1 cum
7,387.23
SAY
₹7,387.25
D-02/SOURCEPRINTED PAGE 1997
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1997

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1997. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.