CPWD Analysis of Rates · New Technologies and Materials
Erection of GFRG Panels in walls in all floors using suitable crane as per instructions of Engineer-in-Charge, as per cutting drawings and structural drawings, in perfect line and plumb, above RCC plinth beam/GFRG panel below and provide necessary lateral/ slanting support to keep the wall panel in safe position, providing & tieing of Reinforcement as per structural drawings and applying a coat of water repellant coating Zycosil/equivalent or equivalent product (1 Zycosil/equivalent compound :10 water ) to saturation level over RCC plinth beam to provide water proofing treatment to joint between wall panel & plinth beam as per the guide lines / instruction by the engineer in charge. (Cost of reinforcement, water proofing of walls and plinth beam/GFRG panel below joints and installation of door/ window frames before filling of concrete shall be paid separately). The rate quoted shall include making provision for laying of lintels, beams, sunshades, staircase beams, lofts, plumbing work, electrical conduits and any structural insertion etc., as per the drawing and direction of the engineer in charge. The payment shall be made based on the actual exposed area (one side only) of the panel. The work shall be carried out as per the Special Conditions For Glass Fibre Reinforced Gypsum (GFRG) Structures mentioned in NIT. Note: i) When cutting panel, “A” side is to be for outside or external surface of respective external wall and B side is to be for internal surface of wall ii)Erection of panel is to be with reference to both building plan & cutting drawing by following notational mark indicated in the cutting drawing as well as notional mark written on each panel cut as per cutting drawing
- Item number
- 26.52
- Analysis basis
- Detail of cost for 36sqm. (4 walls of 3mx3m
- Priced inputs
- 7
- Derived rate
- ₹283.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.52 — Erection of GFRG Panels in walls in all floors using suitable crane as per instructions of Engineer-in-Charge, as per cutting drawings and structural drawings, in perfect line and plumb, above RCC plinth beam/GFRG panel below and provide necessary lateral/ slanting support to keep the wall panel in safe position, providing & tieing of Reinforcement as per structural drawings and applying a coat of water repellant coating Zycosil/equivalent or equivalent product (1 Zycosil/equivalent compound :10 water ) to saturation level over RCC plinth beam to provide water proofing treatment to joint between wall panel & plinth beam as per the guide lines / instruction by the engineer in charge. (Cost of reinforcement, water proofing of walls and plinth beam/GFRG panel below joints and installation of door/ window frames before filling of concrete shall be paid separately). The rate quoted shall include making provision for laying of lintels, beams, sunshades, staircase beams, lofts, plumbing work, electrical conduits and any structural insertion etc., as per the drawing and direction of the engineer in charge. The payment shall be made based on the actual exposed area (one side only) of the panel. The work shall be carried out as per the Special Conditions For Glass Fibre Reinforced Gypsum (GFRG) Structures mentioned in NIT. Note: i) When cutting panel, “A” side is to be for outside or external surface of respective external wall and B side is to be for internal surface of wall ii)Erection of panel is to be with reference to both building plan & cutting drawing by following notational mark indicated in the cutting drawing as well as notional mark written on each panel cut as per cutting drawing — is derived from 7 priced inputs and works out to ₹283.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- = 36 sqm)
- Skilled trained crew erection team 4 persons
- for 4 hour
- For 2 Lintels works, 4 skilled men for 2 hrs
- Web cutting for horizontal tie beam, 2 skilled
- men for 4 hrs
- Placing horizontal tie beam reinforcement 4
- men for 2 hrs
- nical supervisor = Skilled labour)
- Cost for technical supervisor for 4 hrs (Tech-
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 2 | 897.00 | 1,794.00 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0123 | Mason (Brick layer) 1st classMason 1st classLabour | day | 1 | 897.00 | 897.00 |
| 0116 | Fitter (Grade 1)Labour | day | 0.5 | 897.00 | 448.50 |
| 0037 | Mobile craneMachinery | day | 0.375 | 5,050.00 | 1,893.75 |
| 9999 | Hire charge for lateral support & Lifting jawsMaterial | L.S. | 150 | 2.27 | 340.50 |
- TOTAL
- 7,167.75
- Add 1% water charges
- 71.68
- TOTAL
- 7,239.43
- Add GST on “X” (multiplying factor 0.2127)
- 1,539.83
- TOTAL
- 8,779.26
- Add 15% CPOH on “Y”
- 1,316.89
- TOTAL
- 10,096.15
- Add Cess @1% on “Z”
- 100.96
- Cost of 36 sqm
- 10,197.11
- Cost of 1 sqm
- 283.25
- Say
- 283.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1985. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.