Supplying of standard quality GFRG panel of 124 mm thickness with modular cavities purchased from GFRG panel manufacturing plant in the country, cut to required wall sizes and floor/ roof slab sizes in correct length and height, including cutting of door, window and ventilator opening as per the cutting drawing prepared by architects /design engineers for the construction of GFRG building and loaded in stillages for transportation to the construction site. Cost of panel includes security deposits, hire charges of stillages & jaws, cost of transportation in trucks/ lorries without any damages upto 300kms including all leads and lifts from GFRG manufacturing plant to construction site and unloading at site using suitable fork lift/ crane. (Payment shall be made on the basis of area of one side of panel without reduction of opening of door/ window / ventilator). For transportation above 300kms, additional charges to be paid

Item number
26.51
Analysis basis
Detail of cost for 1sqm.
Priced inputs
3
Derived rate
₹1,477.30/ SQM
D-01/RATE ANALYSISITEM 26.51

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.51 (Supplying of standard quality GFRG panel of 124 mm thickness with modular cavities purchased from GFRG panel manufacturing plant in the country, cut to required wall sizes and floor/ roof slab sizes in correct length and height, including cutting of door, window and ventilator opening as per the cutting drawing prepared by architects /design engineers for the construction of GFRG building and loaded in stillages for transportation to the construction site. Cost of panel includes security deposits, hire charges of stillages & jaws, cost of transportation in trucks/ lorries without any damages upto 300kms including all leads and lifts from GFRG manufacturing plant to construction site and unloading at site using suitable fork lift/ crane. (Payment shall be made on the basis of area of one side of panel without reduction of opening of door/ window / ventilator). For transportation above 300kms, additional charges to be paid) is derived from 3 priced inputs and works out to ₹1,477.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Panel area = 1.00sqm, Add wastage @ 5%
  • = 0.050sqm, Total area = 1.05 sqm
ANALYSIS OF RATES · ITEM 26.51DETAIL OF COST FOR 1SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7368MATGFRG panel of 124mm thickGFRG Panel of 124 mm thicksqm1.05896.00940.80
9999MATTransportation of panel in suitable truck (Rs 0.15/sqm/km) upto 300 KmL.S.262.2759.02
9999MATHire Charges for Stillages/Lifting jaw, unloading of panel at site using for lift or crane, Hire Charges for Stillages/Lifting jawL.S.172.2738.59
BUILD-UP TO RATE
TOTAL
1,038.41
Add 1% water charges
+10.38
TOTAL
1,048.79
Add GST on “X” (multiplying factor 0.2127)
+223.08
TOTAL
1,271.87
Add 15% CPOH on “Y”
+190.78
TOTAL
1,462.65
Add Cess @1% on “Z”
+14.63
Cost of 1 sqm
1,477.28
SAY
₹1,477.30
D-02/SOURCEPRINTED PAGE 1984
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1984

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1984. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.