CPWD Analysis of Rates · New Technologies and Materials
Supplying and installation of moisture resistant/fire resistant cement board as per standard sizes fixed with self-drilling / taping screws. Screws shall be of counter sunk rib head of 1.60mm to 4 mm thick or 8 to 10 gauge of length varying from 25 to 45 mm
Cement Fiber Board 6 mm thick as per IS 14862:2000 of type B (High pressure Steam Cured)
- Item number
- 26.45.1
- Analysis basis
- Details of cost for 10 Sqm
- Priced inputs
- 5
- Derived rate
- ₹1,430.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.45.1 — Supplying and installation of moisture resistant/fire resistant cement board as per standard sizes fixed with self-drilling / taping screws. Screws shall be of counter sunk rib head of 1.60mm to 4 mm thick or 8 to 10 gauge of length varying from 25 to 45 mm Cement Fiber Board 6 mm thick as per IS 14862:2000 of type B (High pressure Steam Cured) — is derived from 5 priced inputs for 10 Sqm and works out to ₹1,430.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- For cutting and fixing of Cement & gypsum
- board
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0238 | 6 mm thick fibre cement board 10 sqm +1 sqm (Add for wastage @10%)=11.00 sqm6 mm thick Fibre Cement Board Type A, Category IV as per IS 14862:2000Material | Sqm | 11 | 510.00 | 5,610.00 |
| 2635 | GI screws of gauge 10, length 25 mm for fixing cement fibre board to C section Tapping and finishing Cement board jointsGI Screws of gauge 10, length 25 mm for fixing cement fibre board to C sectionMaterial | each | 40 | 3.30 | 132.00 |
| Filling the Grove of 2 mm to 3 mm between 6 mm and 10 mm thick cement bonded particle boardsRate as per item Sub A/R 1Sub-analysis | Sqm | 10 | 95.40 | 954.00 | |
| 0112 | Carpenter 2nd classLabour | day | 1.11 | 816.00 | 905.76 |
| 0114 | BeldarLabour | day | 3.33 | 736.00 | 2,450.88 |
- TOTAL
- 10,052.64
- Add 1 % Water charges on “W”
- 100.53
- TOTAL
- 10,153.17
- Add GST on “X” (multiplying factor 0.2127)
- 2,159.58
- TOTAL
- 12,312.75
- Add 15% CPOH on “Y”
- 1,846.91
- TOTAL
- 14,159.66
- Add Cess @ 1% on “Z”
- 141.60
- Cost of 10 sqm
- 14,301.26
- Cost of 1 sqm
- 1,430.13
- Say
- 1,430.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1969. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.