Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Providing and fixing in all exterior face panels breathable vapour barrier underneath the cement fiber board as per National Building Code 2009 complete as per direction of Engineerin-charge

Item number
26.44
Analysis basis
Details of cost for 10.00 Sqm
Priced inputs
3
Derived rate
298.75 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.44 Providing and fixing in all exterior face panels breathable vapour barrier underneath the cement fiber board as per National Building Code 2009 complete as per direction of Engineerin-charge — is derived from 3 priced inputs for 10.00 Sqm and works out to ₹298.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 10.00 sqm + 1.00 sqm (Add for wastage
  • @10%) = 11.00 sqm
  • For fixing10 sqm vapour barrier
CodeInputUnitQuantityRate (INR)Amount (INR)
2637Vapour barrierMaterialsqm11184.002,024.00
0112Carpenter 2nd classLabourday0.049816.0039.98
0114BeldarLabourday0.049736.0036.06
TOTAL
2,100.04
Add 1 % Water charges on “W”
21.00
TOTAL
2,121.04
Add GST on “X” (multiplying factor 0.2127)
451.15
TOTAL
2,572.19
Add 15% CPOH on “Y”
385.83
TOTAL
2,958.02
Add Cess @ 1% on “Z”
29.58
Cost of 10 sqm
2,987.60
Cost of 1.00 sqm
298.76
Say
298.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1969. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works