Providing and fixing in all exterior face panels breathable vapour barrier underneath the cement fiber board as per National Building Code 2009 complete as per direction of Engineerin-charge

Item number
26.44
Analysis basis
10.00 Sqm
Priced inputs
3
Derived rate
₹298.75/ SQM
D-01/RATE ANALYSISITEM 26.44

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.44 (Providing and fixing in all exterior face panels breathable vapour barrier underneath the cement fiber board as per National Building Code 2009 complete as per direction of Engineerin-charge) is derived from 3 priced inputs for 10.00 Sqm and works out to ₹298.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10.00 sqm + 1.00 sqm (Add for wastage
  • @10%) = 11.00 sqm
  • For fixing10 sqm vapour barrier
ANALYSIS OF RATES · ITEM 26.44DETAILS OF COST FOR 10.00 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2637MATVapour barriersqm11184.002,024.00
0112LABCarpenter 2nd classday0.049816.0039.98
0114LABBeldarday0.049736.0036.06
BUILD-UP TO RATE
TOTAL
2,100.04
Add 1 % Water charges on “W”
+21.00
TOTAL
2,121.04
Add GST on “X” (multiplying factor 0.2127)
+451.15
TOTAL
2,572.19
Add 15% CPOH on “Y”
+385.83
TOTAL
2,958.02
Add Cess @ 1% on “Z”
+29.58
Cost of 10 sqm
2,987.60
Cost of 1.00 sqm
298.76
SAY
₹298.75
D-02/SOURCEPRINTED PAGE 1969
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1969

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1969. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate