CPWD Analysis of Rates · New Technologies and Materials
Providing at all heights, levels and locations Aluminium profile industrial troughed sheet of Alloy 31500/31000/40800, conforming to IS 1254, IS 737, IS 2676. The sheet shall be fixed using self drilling/self tapping SS screws of size 5.5x65 mm with EPDM seal complete upto required pitch in horizontal, vertical or curved surfaces i/c cutting to size and shape where required as per specifications, detail drawings and direction of Engineer-in-Charge. The rate shall be inclusive of all screws, seal, ridge, labour, scaffolding, machinery for fixing and approved sealent where required etc. but excluding the cost of purlins, rafters and trusses
0.91 mm thick, the profile detail width 1044/920 mm, cover width 1000/875 mm
- Item number
- 26.19.2
- Analysis basis
- Details of cost for 216.14 sqm
- Priced inputs
- 10
- Derived rate
- ₹1,462.90 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.19.2 — Providing at all heights, levels and locations Aluminium profile industrial troughed sheet of Alloy 31500/31000/40800, conforming to IS 1254, IS 737, IS 2676. The sheet shall be fixed using self drilling/self tapping SS screws of size 5.5x65 mm with EPDM seal complete upto required pitch in horizontal, vertical or curved surfaces i/c cutting to size and shape where required as per specifications, detail drawings and direction of Engineer-in-Charge. The rate shall be inclusive of all screws, seal, ridge, labour, scaffolding, machinery for fixing and approved sealent where required etc. but excluding the cost of purlins, rafters and trusses 0.91 mm thick, the profile detail width 1044/920 mm, cover width 1000/875 mm — is derived from 10 priced inputs for 216.14 sqm and works out to ₹1,462.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Consider a shed of 20x10 metres. (External
- dimensions of plinth).
- Area of roof- 20.2x10.70m = 216.14 sqm.
- MATERIAL:
- Sheets used = 20 Nosx10.70mx1.044m =
- 223.42 sqm, Add 3% wastage = 6.70 sqm,
- Total = 230.12sqm
- LABOUR:
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8978 | Aluminium profile sheet 0.91 mmAluminium profile industrial troughed sheet of Alloy 31500/31000/40800, conforming to IS 1254, IS 737, IS 2676, 0.91 mm thick, the profile detail width 1044/920 mm, cover width 1000/875 mm.Material | sqm | 230.12 | 864.00 | 1,98,823.68 |
| 9999 | Carriage of sheetsMaterial | L.S. | 104 | 2.27 | 236.08 |
| 1023 | Galvanised steel J or L hooks 8 mm diaMaterial | 10 Nos | 47.6 | 130.00 | 6,188.00 |
| 1208 | Bitumen washerMaterial | 100 Nos | 4.76 | 30.00 | 142.80 |
| 1209 | G.I. plain washer thickMaterial | 100 Nos | 4.76 | 35.00 | 166.60 |
| 9999 | Carriage of bolts and nuts, washers etc.Material | L.S. | 8.06 | 2.27 | 18.30 |
| 9999 | SundriesMaterial | L.S. | 39.52 | 2.27 | 89.71 |
| 0130 | MistryLabour | day | 2.34 | 897.00 | 2,098.98 |
| 0112 | Carpenter 2nd classLabour | day | 9.34 | 816.00 | 7,621.44 |
| 0114 | BeldarLabour | day | 9.34 | 736.00 | 6,874.24 |
- TOTAL
- 2,22,259.83
- Add 1 % Water charges on “W”
- 2,222.60
- TOTAL
- 2,24,482.43
- Add GST on “X” (multiplying factor 0.2127)
- 47,747.41
- TOTAL
- 2,72,229.84
- Add 15% CPOH on “Y”
- 40,834.48
- TOTAL
- 3,13,064.32
- Add Cess @ 1% on “Z”
- 3,130.64
- Cost of 216.14 sqm
- 3,16,194.96
- Cost of 1 sqm
- 1,462.92
- Say
- 1,462.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1935. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works