Mortar in lime, surkhi (50% red and 50% light yellow) and marble dust 1:1.5:0.5

Item number
3.19
Analysis basis
10 cum
Priced inputs
7
Derived rate
₹2,880.65/ CUM
D-01/RATE ANALYSISITEM 3.19

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 3.19 (Mortar in lime, surkhi (50% red and 50% light yellow) and marble dust 1:1.5:0.5) is derived from 7 priced inputs for 10 cum and works out to ₹2,880.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (0.475 cum of lime putty) = 3.01 q of unslaked lime
ANALYSIS OF RATES · ITEM 3.19DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1182MATSurkhicum7.125778.005,543.25
0773MATUnslaked limequintal30.1325.009,782.50
0784MATMarble dust/ powdercum2.41,180.002,832.00
0114LABBeldarday9736.006,624.00
0101LABBhistiday4.5816.003,672.00
9999MATAs cost for running and upkeep of mortar millL.S.103.52.27234.95
9999MATSundriesL.S.522.27118.04
BUILD-UP TO RATE
Cost of 10.00 cum
28,806.74
Cost of 1.00 cum
2,880.67
SAY
₹2,880.65
D-02/SOURCEPRINTED PAGE 148
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
148

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 148. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.